Pune/Project record

MahaRERA · the public record

Lotus Pinnacle

Mamurdi · Swayambhu Estates

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100002384

Delivery and registration

When is the project declared for completion?

Lotus Pinnacle is registered with MahaRERA as P52100002384 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100002384
Registered on31 Jul 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Lotus Pinnacle record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Swayambhu Estates is the promoter of record on 10 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

10projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Lotus Pinnacle in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
A Wing1G+1330 Dec 2022
A1 Wing1G+1330 Dec 2022
B Wing1G+1330 Dec 2022

Legal and disputes

What disputes are disclosed?

11 complaints are on the MahaRERA record for Lotus Pinnacle, with orders passed in 6 of them.

11complaints

6with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000006491421/12/2020NAVNATH PANDURANG RAUT AND OTHERS vs SWAYAMBHU ESTATEorder passed
CC00500000008557708/06/2021Dhushyant Singh Rana vs Swayambhu Estate through its partner Balasaheb Tarasorder passed
CC00500000008564810/06/2021Supriya Diwakar Prasad vs Swayambhu Estatesthrough its partner Balasaheb Tarasorder passed
CC00500000008567813/06/2021Laxmansingh Rawat vs Swayambhu Estate through its partner Balasaheb Taraspending / no order on file
CC00500000008568613/06/2021Vijay Dnyandeo Lad vs Swayambhu Estate through its partner Balasaheb Tarasorder passed
CC00500000009576611/07/2021Hayat Singh vs Swayambhu Estate through its partner Balasaheb Taraspending / no order on file
CC00500000009609106/10/2021Rahul Popatrao Babar vs Swayambhu Estate through its partner Balasaheb jaywant Taraspending / no order on file
CC00500000009609612/10/2021Dilip Shivaji Naik vs Swayambhu Estate through its partner Balasaheb Taras and othersorder passed
CC00500000009611009/10/2021Tushar Laxman Chaure vs Swayambhu Estate through its partner Balasaheb jaywant Taraspending / no order on file
CC00500000009611710/10/2021Sagar Vilas Bhasme vs Swayambhu Estate through its partner Balasaheb Taraspending / no order on file
CC00500000010650924/01/2022Bhagoji Rajaram Kokitkar vs Swayambhu Estate through its partner Balasaheb jaywant Tarasorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2023In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reas

Location, Land & Connectivity

Located at Mamurdi, Mamuirdi, Haveli, Pune, 412101. Per the filed land record, the plot is bounded to the north by 20 Ft road, to the south by Part of Sy No 17, to the east by Part of Sy No 17 and to the west by Survey number 15. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~10 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park10 km
Baner–Balewadi belt15 km
Pune Junction / city centre24 km
Pune Int'l Airport (Lohegaon)24 km
Kharadi / EON IT Park28 km
Magarpatta / Hadapsar IT29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ravet

City ONE Skyve
possession by Sep 2026 · Shree SAI Capital
Godrej Carnival
possession by Sep 2026 · Godrej Skyline Developers Limited
Godrej Nurture
possession by Sep 2026 · Godrej Skyline Developers Limited
Madhuban
possession by Sep 2026 · Godrej Skyline Developers Limited
OM Mangalam Chaitanya
possession by Sep 2026 · Shri Associates
OM Mangalam Disha
possession by Sep 2026 · Shri Associates

Major developers building in Ravet

Other RERA-registered projects in Pune

Lotus Plaza
possession by Dec 2027 · Ekvira Properties
Lotus Residency
declared completion Mar 2018 · Labhdevelopers
Lotus Serenity
possession by Dec 2027 · Vulcan Infrastructure
Lotus Seva
possession by Mar 2029 · Lotus Landmarks
Lotus Shalaka
possession by Dec 2027 · Lotus Spaces
Lotus Sheetal
possession by Dec 2026 · Lotus Landmarks

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026