Maavi Shree Ashirwad

P52100080158 · Kothrud-South · promoter Maavi Spaces Unit

Certificate SignedDue 31 Dec 2030

Delivery & Registration

MahaRERA registrationP52100080158
Registered on02 May 2025
Promoter-declared completion31 Dec 2030
Current statusCertificate Signed
Against today53 months to the declared date

Construction Progress

MahaRERA's cost filing puts construction at ~22.5% of the estimated project cost incurred as of the last certificate (₹6.74 Cr spent against a ₹30.00 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 25 homes filed with MahaRERA, 3 are sold/booked and 22 remain available (~12% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹4.19 Cr in agreement value so far. Of that, ₹2.10 Cr (~50%) is already collected, ₹2.09 Cr receivable — a read on how far along these sales really are. Note: the project registers 60 homes in total, but this sold/unsold inventory filing covers only 25 of them — the other 35 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1A-101924 sqft (85.84 sqm)₹1.15 Cr
Floor 1A-103924 sqft (85.84 sqm)₹1.15 Cr
Floor 1B-102983 sqft (91.32 sqm)₹1.22 Cr
Floor 1B-103850 sqft (78.97 sqm)₹1.05 Cr
Floor 1B-104983 sqft (91.32 sqm)₹1.22 Cr
Floor 1B-105983 sqft (91.32 sqm)₹1.22 Cr
Floor 2B-202983 sqft (91.32 sqm)₹1.22 Cr
Floor 2B-204983 sqft (91.32 sqm)₹1.22 Cr
Floor 3A-303924 sqft (85.84 sqm)₹1.15 Cr
Floor 3B-302983 sqft (91.32 sqm)₹1.22 Cr
Floor 4B-402983 sqft (91.32 sqm)₹1.22 Cr
Floor 5B-5011,023 sqft (95.04 sqm)₹1.27 Cr
Floor 5B-5021,023 sqft (95.04 sqm)₹1.27 Cr
Floor 5B-503885 sqft (82.22 sqm)₹1.10 Cr
Floor 5B-5041,023 sqft (95.04 sqm)₹1.27 Cr
Floor 5B-506885 sqft (82.22 sqm)₹1.10 Cr
Floor 6B-6011,023 sqft (95.04 sqm)₹1.27 Cr
Floor 6B-6021,023 sqft (95.04 sqm)₹1.27 Cr
Floor 6B-603885 sqft (82.22 sqm)₹1.10 Cr
Floor 6B-6041,023 sqft (95.04 sqm)₹1.27 Cr
Floor 6B-6051,023 sqft (95.04 sqm)₹1.27 Cr
Floor 6B-606885 sqft (82.22 sqm)₹1.10 Cr

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6 and 60 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Wing A1G+624-
Wing B1G+636-

Unit mix on the filing: 60 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202731 Dec 2030We, Maavi Spaces Unit 1, the promoter of the project Maavi Shree Ashirwad (Registration No. P52100080158) under MahaRERA, hereby submit our request for an extension of time for the

Location, Land & Connectivity

Located at Kothrud-South , CTS No- 675 P, Pune City, Pune, 411038. Per the filed land record, the plot is bounded to the north by By Portion of Survey No 11 LIC Vinit Co-Operati, to the south by Survey No 9 Part, to the east by Open Space and to the west by Part of 9-3-3-A of Shri R V Bajaj. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre7 km
Baner–Balewadi belt8 km
Magarpatta / Hadapsar IT12 km
Hinjewadi Rajiv Gandhi IT Park13 km
Pune Int'l Airport (Lohegaon)14 km
Kharadi / EON IT Park14 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kothrud

Umed
possession by Jul 2026 · Runwal Realtors Pvt Ltd
Chandra Apartment
possession by Aug 2026 · Deshpande Landmark Private Limited
Keshar
possession by Aug 2026 · Badhekar Properties
Tungabhadra CO OP HSG SOC
possession by Aug 2026 · Not Available
Arunali
possession by Sep 2026 · Badhekar Properties
Guruvaibhav CO-Op.housing Society Limited
possession by Sep 2026 · Shreepad Associates

Major developers building in Kothrud

Other RERA-registered projects in Pune

Maavi Shree Shivgauri
possession by Dec 2030 · Maavi Porwal Spaces Unit 2 LLP
Madhav Apartment
declared completion Mar 2025 · Eagle Prestige
Madhav Park
possession by Dec 2026 · Shreeyash Builders AND Developers
Madhuban
declared completion Mar 2018 · M/s Kakkad Developments
Madhuban
possession by Dec 2026 · Pass Developers
Madhuban
declared completion Dec 2021 · Prashant Ramchandra Harsule

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026