MahaRERA · the public record
Mauli Niwas
Kothrud · Varadayini Constructions
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Oct 2019
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52100001950
Delivery and registration
When is the project declared for completion?
Mauli Niwas is registered with MahaRERA as P52100001950 and the promoter has declared completion for 31 Oct 2019.
31 Oct 2019
declared completion
83months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52100001950 |
| Registered on | 31 Jul 2017 |
| Promoter-declared completion | 31 Oct 2019 |
| Current status | Certificate Signed |
| Against today | about 83 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Mauli Niwas record 10 quarterly progress reports since registration.
10quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Completion date lapsed — the registered completion date has lapsed without a recorded finish.
- Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for Mauli Niwas in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| Mauli Niwas | 1 | G+5 | 31 Mar 2019 |
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 31 Oct 2019 | TDR was applied as per new DCR which was approved. A revised plan submitted with the additional 4th-floor plan. The revised plan was also approved by the competent authority. Comme |
Location, Land & Connectivity
Located at Kothrud, Kothrud, Haveli, Pune, 411038. Per the filed land record, the plot is bounded to the north by plot no 37, to the south by colony road, to the east by colony road and to the west by plot no 35. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Baner–Balewadi belt | 6 km |
| Pune Junction / city centre | 9 km |
| Hinjewadi Rajiv Gandhi IT Park | 11 km |
| Magarpatta / Hadapsar IT | 14 km |
| Pune Int'l Airport (Lohegaon) | 16 km |
| Kharadi / EON IT Park | 16 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.