Pune/Project record

MahaRERA · the public record

MAYAKA CLASSIC-ABC

Punawale · UMESH MANOHARRAO WAKODE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100013988

Delivery and registration

When is the project declared for completion?

MAYAKA CLASSIC-ABC is registered with MahaRERA as P52100013988 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100013988
Registered on07 Nov 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MAYAKA CLASSIC-ABC record 17 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 17 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Umesh Manoharrao Wakode is the promoter of record on 8 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

8projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for MAYAKA CLASSIC-ABC in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
A1G+730 Jun 2021
B1G+530 Jun 2021
C1G+730 Jun 2021

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for MAYAKA CLASSIC-ABC, with orders passed in 5 of them.

5complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000001167825/06/2018VIKRAM SONAWANE vs UMESH MANOHARRAO WAKODEorder passed
CC00500000006495720/12/2020Vikram Sonawane vs Umesh Wakodeorder passed
CC00500000006495520/12/2020Ajay Bansod vs Umesh Manoharrao Wakodeorder passed
CC00500000031044921/02/2024PRASHANT DEEPAK GODKE vs M/S.WAZARKAR ENTERPRISESorder passed
CC00500000017792812/12/2022prasad balasaheb kenjale vs UMESH MANOHARRAO WAKODEorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020Disputes, as mentioned in MAHARERA complaint no 11678 and settelment of the same along with road development, delayed the process for application of occupancy certificate. The proc

Location, Land & Connectivity

Located at Punawale, Haveli, Pune, 411033. Per the filed land record, the plot is bounded to the north by CTS 208, to the south by CTS NO 169, to the east by BY PROPERTY CTS NO 216 and to the west by CTS 229. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~97 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park97 km
Baner–Balewadi belt102 km
Pune Int'l Airport (Lohegaon)112 km
Pune Junction / city centre112 km
Kharadi / EON IT Park116 km
Magarpatta / Hadapsar IT117 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Umesh Manoharrao Wakode is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Umesh Manoharrao Wakode

Umesh Manoharrao Wakode
Past its declared completion datePune

Other RERA-registered projects in Punawale

Vision ACE Commercial Phase I
possession by Sep 2026 · Vision ACE
7 Plumeria Drive- Phase 3
possession by Sep 2026 · B A Consulting
Austin Arena
possession by Sep 2026 · Austin Real Infra LLP
Shree Heritage
possession by Sep 2026 · Bhakti Venkateshwara Developers
Silveroak C1
Deregistered by MahaRERA · possession by Sep 2026 · SAI Samarttha Properties
Vivanta Next
possession by Sep 2026 · Shree Sonigara Punamiya Developers

Major developers building in Punawale

Other RERA-registered projects in Pune

Mayfair
possession by Dec 2030 · City Ethernal LLP
Mayfair Residences Phase 1
possession by Jun 2029 · Mantra Residencies Erika Private Limited
Mayfair Residences Phase 2
possession by Jun 2029 · Mantra Residencies Erika Private Limited
Mayflower
possession by Jun 2027 · Pandit Javdekar Associates
Mayuk
possession by Mar 2031 · Mayur Corporation
Mayur Geminus Wing A
possession by Dec 2030 · Bunty Properties Unit NO. XI

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026