Pune/Project record

MahaRERA · the public record

Misty Winds 2

Karanjgaon · Planet I Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100018819

Delivery and registration

When is the project declared for completion?

Misty Winds 2 is registered with MahaRERA as P52100018819 and the promoter has declared completion for 30 Sep 2023.

30 Sep 2023

declared completion

36months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100018819
Registered on06 Dec 2018
Promoter-declared completion30 Sep 2023
Current statusCertificate Signed
Against todayabout 36 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Misty Winds 2 record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Planet Developers is the promoter of record on 19 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

19projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In Misty Winds 2, 71 of 128 plots filed with MahaRERA are recorded as sold or booked, about 55%, and 57 remain available.

55%sold

71 of 128 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Misty Winds 2 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Sep 2023There were some delays happened in completion of the project but it was due to ups and downs for the Indian Real Estate Sector due to corona pandemic. There was liquidity crisis i

Location, Land & Connectivity

Located at Karanjgaon, Survey No 71/2 or 79/2, Haveli, Pune, 410405. Per the filed land record, the plot is bounded to the north by Survey No 79 and 71-1, to the south by Survey No 71-3 and 71-5, to the east by Survey No 70 and to the west by Survey No 75 and 76. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~33 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park33 km
Baner–Balewadi belt38 km
Pune Junction / city centre48 km
Pune Int'l Airport (Lohegaon)48 km
Kharadi / EON IT Park52 km
Magarpatta / Hadapsar IT53 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Planet I Developers is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Kamshet

Aranya
possession by Dec 2026 · Karmaa Builders
Forisaqua - Phase 2
possession by Dec 2026 · Vijay Kumar Ratanchand Javeri
Stellar 8
possession by Dec 2026 · Iraah Lifespaces LLP
Antaaya Villas
possession by Dec 2027 · Antaaya Builders LLP
Palaash Valley
possession by Dec 2027 · Good Will Developper
Divine Wonders
possession by Dec 2028 · M/S Zircon Properties

Major developers building in Kamshet

Other RERA-registered projects in Pune

Mithila Harmony
possession by Dec 2026 · Shree Bhagwati Infra
Mithila Residency
declared completion Mar 2026 · Santosh Kumar Jha
Mithila Residency
declared completion Apr 2026 · Shreeyash Associates
Mitrakunj
declared completion Dec 2024 · Kishor B Sancheti
Mitti Grama
declared completion Jan 2026 · Redsoil Builders LLP
Mizura Residences By Esbee
possession by Jun 2030 · Esbee Greenspaces LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026