Pune/Project record

MahaRERA · the public record

Mohar Srushti

Near Katraj dairy · Mohar Projects LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2030declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2030

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100051231

Delivery and registration

When is the project declared for completion?

Mohar Srushti is registered with MahaRERA as P52100051231 and the promoter has declared completion for 31 Dec 2030.

31 Dec 2030

declared completion

51months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100051231
Registered on08 Jun 2023
Promoter-declared completion31 Dec 2030
Current statusCertificate Signed
Against today51 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Mohar Srushti record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Mohar Projects Llp is the promoter of record on 20 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

20projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In Mohar Srushti, 5 of 54 plots filed with MahaRERA are recorded as sold or booked, about 9%, and 49 remain available.

9%sold

5 of 54 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Mohar Srushti in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Near Katraj dairy, Pune Mumbai Old Higway, Pune City, Pune, 410405. Per the filed land record, the plot is bounded to the north by Gat No 18 and others, to the south by Gat No 26 and other, to the east by Road and to the west by Gavthan and Gat no 20 and others. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~48 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park48 km
Baner–Balewadi belt51 km
Pune Junction / city centre60 km
Magarpatta / Hadapsar IT66 km
Pune Int'l Airport (Lohegaon)66 km
Kharadi / EON IT Park68 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kamshet

Aranya
possession by Dec 2026 · Karmaa Builders
Forisaqua - Phase 2
possession by Dec 2026 · Vijay Kumar Ratanchand Javeri
Stellar 8
possession by Dec 2026 · Iraah Lifespaces LLP
Antaaya Villas
possession by Dec 2027 · Antaaya Builders LLP
Palaash Valley
possession by Dec 2027 · Good Will Developper
Divine Wonders
possession by Dec 2028 · M/S Zircon Properties

Major developers building in Kamshet

Other RERA-registered projects in Pune

Mokate Kalanidhi
possession by Dec 2028 · Sharada Alliance Promoters & Builder
Monaarch Liviano
declared completion Dec 2022 · Rahul Gowardhan Kadam
Monarch Regal AND Majestic
possession by Dec 2028 · Monarch Builders AND Developers
Monarque BY VTP Luxe Phase 2
possession by Dec 2029 · Mexus Real Estate Developers LLP
Monarque BY VTP Luxe Phase 3
possession by Dec 2030 · Mexus Real Estate Developers LLP
Mont Vert Axis
possession by Dec 2028 · Mont Vert Needs

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026