MahaRERA Property Intelligence · Pune

Neo 95

P52100078212 · Ravet · promoter Infra

Certificate SignedDue 31 Jul 2025

Delivery & Registration

MahaRERA registrationP52100078212
Registered on29 Nov 2024
Promoter-declared completion31 Jul 2025
Current statusCertificate Signed
Against todayabout 12 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Sales & Inventory

Of 39 homes filed with MahaRERA, 0 are sold/booked and 39 remain available (~0% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1101595 sqft (55.29 sqm)₹38.80 Lakh
Floor 1102440 sqft (40.87 sqm)₹28.68 Lakh
Floor 1103541 sqft (50.25 sqm)₹35.27 Lakh
Floor 1104666 sqft (61.86 sqm)₹43.41 Lakh
Floor 22011,046 sqft (97.15 sqm)₹68.18 Lakh
Floor 2202625 sqft (58.03 sqm)₹40.73 Lakh
Floor 2203440 sqft (40.87 sqm)₹28.68 Lakh
Floor 2204541 sqft (50.25 sqm)₹35.27 Lakh
Floor 2205666 sqft (61.87 sqm)₹43.42 Lakh
Floor 33011,046 sqft (97.15 sqm)₹68.18 Lakh
Floor 3302625 sqft (58.03 sqm)₹40.73 Lakh
Floor 3303440 sqft (40.87 sqm)₹28.68 Lakh
Floor 3304541 sqft (50.25 sqm)₹35.27 Lakh
Floor 3305666 sqft (61.87 sqm)₹43.42 Lakh
Floor 44011,046 sqft (97.15 sqm)₹68.18 Lakh
Floor 4402625 sqft (58.03 sqm)₹40.73 Lakh
Floor 4403440 sqft (40.87 sqm)₹28.68 Lakh
Floor 4404541 sqft (50.25 sqm)₹35.27 Lakh
Floor 4405479 sqft (44.51 sqm)₹31.24 Lakh
Floor 55011,046 sqft (97.15 sqm)₹68.18 Lakh
Floor 5502625 sqft (58.03 sqm)₹40.73 Lakh
Floor 5503440 sqft (40.87 sqm)₹28.68 Lakh
Floor 5504541 sqft (50.25 sqm)₹35.27 Lakh
Floor 5505479 sqft (44.51 sqm)₹31.24 Lakh
Floor 66011,046 sqft (97.15 sqm)₹68.18 Lakh
Floor 6602625 sqft (58.03 sqm)₹40.73 Lakh
Floor 6603440 sqft (40.87 sqm)₹28.68 Lakh
Floor 6604541 sqft (50.25 sqm)₹35.27 Lakh
Floor 6605666 sqft (61.87 sqm)₹43.42 Lakh
Floor 77011,046 sqft (97.15 sqm)₹68.18 Lakh
Floor 7702625 sqft (58.03 sqm)₹40.73 Lakh
Floor 7703440 sqft (40.87 sqm)₹28.68 Lakh
Floor 7704541 sqft (50.25 sqm)₹35.27 Lakh
Floor 7705666 sqft (61.87 sqm)₹43.42 Lakh
Stilt01691 sqft (64.17 sqm)₹47.47 Lakh
Stilt02723 sqft (67.18 sqm)₹49.70 Lakh
Stilt03403 sqft (37.41 sqm)₹27.68 Lakh
Stilt04457 sqft (42.49 sqm)₹31.43 Lakh
Stilt05218 sqft (20.21 sqm)₹14.95 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8 and 39 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Building A1G+839-

Unit mix on the filing: 39 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Mar 202531 Jul 2025The delay in the project’s timeline has been primarily due to unforeseen labor shortages and financial constraints. The shortage of skilled and unskilled labor, caused by challenge

Location, Land & Connectivity

Located at Ravet, Ravet, Haveli, Pune, 412101. Per the filed land record, the plot is bounded to the north by By plot no 8 And By Plot No 25, to the south by By Plot No 10 And By Plot No 23, to the east by By 24 Mtr Road And By Plot No 9 and to the west by By plot no 24 And By 15 ft internal road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every V J Infra project & its RERA track record →

Other RERA-registered projects in Ravet

Shivratna
possession by Jul 2026 · Mr Rajan Vishram Palekar
Glorious Tathastu
possession by Jul 2026 · Glorious Buildcon
Aqua Life
possession by Aug 2026 · Legacy Lifespaces LLP
City ONE Skyve
possession by Sep 2026 · Shree SAI Capital
Godrej Carnival
possession by Sep 2026 · Godrej Skyline Developers Limited
Godrej Nurture
possession by Sep 2026 · Godrej Skyline Developers Limited

Major developers building in Ravet

Other RERA-registered projects in Pune

NEO City Part 2
declared completion Dec 2021 · Mahalaxmi Shelters
Neo City Part 3
possession by Dec 2026 · Mahalaxmi Shelters
Neon
declared completion Jul 2025 · Yashcon Urban Development LLP
Neopolis
possession by Dec 2030 · Nirman Greens Unity LLP
Nest
declared completion Dec 2021 · Skyline Enterprises
Nest Elite
possession by Dec 2027 · Landge Borhade Realtors

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026