MahaRERA Property Intelligence · Pune

Nitin Residency

P52100079051 · Pavana Nagar · promoter Nmk Associates Private

Certificate SignedDue 31 Dec 2027

Delivery & Registration

MahaRERA registrationP52100079051
Registered on03 Feb 2025
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today17 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Nmk Associates Private is the promoter of record on 4 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~26.2% of the estimated project cost incurred as of the last certificate (₹1.14 Cr spent against a ₹4.37 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 8 homes filed with MahaRERA, 0 are sold/booked and 8 remain available (~0% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Note: the project registers 18 homes in total, but this sold/unsold inventory filing covers only 8 of them — the other 10 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1101381 sqft (35.37 sqm)₹23.82 Lakh
Floor 1102397 sqft (36.84 sqm)₹24.81 Lakh
Floor 1103379 sqft (35.21 sqm)₹23.71 Lakh
Floor 1104390 sqft (36.24 sqm)₹24.40 Lakh
Floor 1105472 sqft (43.89 sqm)₹29.56 Lakh
Floor 1106366 sqft (34.04 sqm)₹22.92 Lakh
Floor 3305472 sqft (43.89 sqm)₹29.56 Lakh
Floor 3306366 sqft (34.04 sqm)₹22.92 Lakh

⚠ The inventory filing also declares: 10 not for sale. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2 and 18 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
A1G+218-

Unit mix on the filing: 18 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Pavana Nagar, Chinchwad, Haveli, Pune, 411033. Per the filed land record, the plot is bounded to the north by CTS No 1891 Kolekar-Deshmane-Newase Property, to the south by CTS No 1867 Property of Vaishali Bhokare, to the east by 9M D P Road and to the west by CTS No 1892 Plot No 94 Property of Bhatewara. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~39 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Baner–Balewadi belt39 km
Hinjewadi Rajiv Gandhi IT Park40 km
Pune Junction / city centre44 km
Magarpatta / Hadapsar IT48 km
Kharadi / EON IT Park51 km
Pune Int'l Airport (Lohegaon)52 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Punawale

BVM Flora
possession by Jul 2026 · Sunny Naresh Nagdev
Miracle Mathura
possession by Jul 2026 · Miracle Builders And Developers
Sai Aarav
possession by Jul 2026 · Abhijit Prakash Borase
Samarth Paradise
possession by Aug 2026 · Samarth Associates
Isle OF Life - Building B And C
possession by Aug 2026 · R R Ventures
Vision ACE Commercial Phase I
possession by Sep 2026 · Vision ACE

Major developers building in Punawale

Other RERA-registered projects in Pune

Nitish Lambodar
declared completion Dec 2024 · LB Associates
Nityanand Heights
declared completion Dec 2025 · Kishor Shrihari Mate
Nivaan Grandeur
possession by Jun 2027 · Vishal Ashok Chugera
Nivaan Grandeur Phase-II
possession by Mar 2031 · Vishal Ashok Chugera
Nivaan Legacy
possession by May 2027 · Vishal Ashok Chugera
Nivaan Meadows
possession by Dec 2026 · Vishal Chugera Properties India Private

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026