MahaRERA Property Intelligence · Pune

NITYANAND HEIGHTS

P52100020017 · RAVET · promoter Kishor Shrihari Mate

Certificate SignedDue 30 Dec 2025

Delivery & Registration

MahaRERA registrationP52100020017
Registered on19 Mar 2019
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Kishor Shrihari Mate is the promoter of record on 6 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
NITYANAND HEIGHTS1G+401 Feb 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202530 Dec 2025Due to Finacial problem, i am unable to complete the project as per previous proposed completion date. Request you to grant me extension to be able to completion project in time.
30 Dec 202531 Jan 2021Due to Covid and Labour problem, i am unable to complete the project as per previous proposed completion date. Request you to grant me extension to be able to completion project in

Location, Land & Connectivity

Located at RAVET, RAVET, Haveli, Pune, 412101. Per the filed land record, the plot is bounded to the north by SHRI KANCHAN BUILDING, to the south by SHRI SHENDURKAR PROPERTIES, to the east by S NO 114 and to the west by ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ravet

Shivratna
possession by Jul 2026 · Mr Rajan Vishram Palekar
Glorious Tathastu
possession by Jul 2026 · Glorious Buildcon
Aqua Life
possession by Aug 2026 · Legacy Lifespaces LLP
City ONE Skyve
possession by Sep 2026 · Shree SAI Capital
Godrej Carnival
possession by Sep 2026 · Godrej Skyline Developers Limited
Godrej Nurture
possession by Sep 2026 · Godrej Skyline Developers Limited

Major developers building in Ravet

Other RERA-registered projects in Pune

Nivaan Grandeur
possession by Jun 2027 · Vishal Ashok Chugera
Nivaan Grandeur Phase-II
possession by Mar 2031 · Vishal Ashok Chugera
Nivaan Legacy
possession by May 2027 · Vishal Ashok Chugera
Nivaan Meadows
possession by Dec 2026 · Vishal Chugera Properties India Private
Nivaan Meadows Phase III
possession by Dec 2032 · Vishal Chugera Properties India Private
Nivaan Medows
possession by Dec 2026 · Vishal Chugera Properties India Private

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026