Pune/Project record

MahaRERA · the public record

PANCHRATNA HILLS

katraj · PANCHRATNA ASSOCIATES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Apr 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Apr 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100016204

Delivery and registration

When is the project declared for completion?

PANCHRATNA HILLS is registered with MahaRERA as P52100016204 and the promoter has declared completion for 30 Apr 2023.

30 Apr 2023

declared completion

41months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100016204
Registered on23 Apr 2018
Promoter-declared completion30 Apr 2023
Current statusCertificate Signed
Against todayabout 41 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PANCHRATNA HILLS record 21 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Panchratna Associates is the promoter of record on 12 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

12projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PANCHRATNA HILLS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
a1G+830 Apr 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at katraj, katraj, Haveli, Pune, 411046. Per the filed land record, the plot is bounded to the north by 18 m road, to the south by 48 part, to the east by 49 part and to the west by 49 part. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Pune Junction / city centre10 km
Magarpatta / Hadapsar IT11 km
Kharadi / EON IT Park15 km
Baner–Balewadi belt16 km
Pune Int'l Airport (Lohegaon)17 km
Hinjewadi Rajiv Gandhi IT Park21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ambegaon Bk

Amits Bloomfield Phase III - J AND K Building
possession by Sep 2026 · Amit Enterprises Housing Limited
Ankur Residency
possession by Oct 2026 · Ankur Developers
Astonia Royale Phase III - P Building
possession by Oct 2026 · Amit Enterprises Housing Limited
Airavat B Wing
possession by Nov 2026 · Ashtavinayak Developers
Rajyog C Wing
possession by Dec 2026 · Santosh Shankar Tathe
Deveshwar Tekadi- Phase I- Building: A,b,c,d,e
Not filing quarterly progress reports · possession by Dec 2026 · Mahadrishti Spaces LLP

Major developers building in Ambegaon Bk

Other RERA-registered projects in Pune

Panchratna Hills Phase 2
declared completion Jun 2026 · Panchratna Construction
Panchsheel Garden Building - A
declared completion Jun 2025 · Shankar Dattatray Kemse
Panchsheel Garden Building B
possession by May 2027 · Shankar Dattatray Kemse
Panchshil Avenue
possession by Dec 2026 · New Level Business LLP
Panchshil Towers
possession by Dec 2026 · Panchshil Infrastructure Holdings Pvt. L
Panchtatva
possession by Dec 2026 · Sanskruti Pinnacle

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026