Pune/Project record

MahaRERA · the public record

PRAANGAN

BORADEWADI · K.DHAMALE INFRASTRUCTURE & DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100008629

Delivery and registration

When is the project declared for completion?

PRAANGAN is registered with MahaRERA as P52100008629 and the promoter has declared completion for 31 Jul 2023.

31 Jul 2023

declared completion

38months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100008629
Registered on19 Aug 2017
Promoter-declared completion31 Jul 2023
Current statusCertificate Signed
Against todayabout 38 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PRAANGAN record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 25 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Dhamale Infrastructure Developers is the promoter of record on 7 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

7projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PRAANGAN in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
PRAANGAN B1G+11-
PRAANGAN A1G+4-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for PRAANGAN, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000047144603/08/2024Aparna Pramod Joshi vs K. DHAMALE INFRASTRUCTURES AND DEVELOPERSorder passed
CC00500000047148607/08/2024Sunita Balasaheb Joshi vs K. Dhamale Infrastructures and Developersorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Judge Junior Division Pimpri86/20142014Hearing On Court Commission Report Pending

Location, Land & Connectivity

Located at BORADEWADI, BORADEWADI, Haveli, Pune, 411038. Per the filed land record, the plot is bounded to the north by Gat 315, to the south by Gat 328, to the east by Pune Nashik Highway and to the west by Nala. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~120 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park120 km
Baner–Balewadi belt125 km
Pune Junction / city centre135 km
Pune Int'l Airport (Lohegaon)135 km
Kharadi / EON IT Park139 km
Magarpatta / Hadapsar IT140 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kothrud

Arunali
possession by Sep 2026 · Badhekar Properties
Guruvaibhav CO-Op.housing Society Limited
possession by Sep 2026 · Shreepad Associates
Prathamesh Co-Op Housing Soc
possession by Sep 2026 · Joshi Associates
State Bank OF India Snehdeep Chsl
possession by Sep 2026 · Kotibhaskar Infrastructures &develop
Vaibhavshree AND Indira Priyadarshani
possession by Sep 2026 · Pride Properties & Infrastructure
Yakshanagari CO Operative Housing Society LTD
possession by Sep 2026 · VSA Intezine LLP

Major developers building in Kothrud

Other RERA-registered projects in Pune

Prabha Heights
declared completion Dec 2023 · Rakesh Babulal Solanki
Prabha Madhav Residency
possession by Mar 2028 · Not Available
Prabhangan
possession by Nov 2030 · Ashtekar Constructions
Prabhas
possession by Apr 2027 · Nidisha Buildcon LLP
Prabhat
declared completion Apr 2026 · Pradeep Munot
Prabhat Garima
possession by Apr 2029 · Pandit Javdekar Associates

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026