Pragati Arista

P52100045874 · Moshi · promoter Prakash Samiksha Realty

Certificate SignedDue 30 Jun 2026

Delivery & Registration

MahaRERA registrationP52100045874
Registered on15 Jun 2022
Promoter-declared completion30 Jun 2026
Current statusCertificate Signed
Against todayabout 1 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Construction Progress

MahaRERA's cost filing puts construction at ~35.7% of the estimated project cost incurred as of the last certificate (₹7.50 Cr spent against a ₹21.00 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows. The declared completion date has already passed while the cost-incurred filing sits at ~35.7% — a wide gap between the promise and the money actually spent on site.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 75 homes filed with MahaRERA, 35 are sold/booked (29 with registered agreements + 6 booked) and 40 remain available (~47% sold) — selling steadily. Buyers have committed ₹14.59 Cr in agreement value so far. Of that, ₹8.48 Cr (~58%) is already collected, ₹6.11 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 35 registered agreements, the effective carpet rate is ₹6,525/sqft (typical range ₹6,069–₹14,720) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1101249 sqft (23.17 sqm)₹15.36 Lakh
Floor 1102632 sqft (58.72 sqm)₹31.14 Lakh
Floor 1102233 sqft (21.61 sqm)₹14.33 Lakh
Floor 1103229 sqft (21.24 sqm)₹14.08 Lakh
Floor 1103624 sqft (57.94 sqm)₹30.73 Lakh
Floor 1104238 sqft (22.09 sqm)₹14.64 Lakh
Floor 1104624 sqft (57.94 sqm)₹30.73 Lakh
Floor 1105238 sqft (22.09 sqm)₹14.64 Lakh
Floor 1105632 sqft (58.72 sqm)₹31.14 Lakh
Floor 1106238 sqft (22.09 sqm)₹14.64 Lakh
Floor 1107238 sqft (22.09 sqm)₹14.64 Lakh
Floor 1108238 sqft (22.09 sqm)₹14.64 Lakh
Floor 1109229 sqft (21.24 sqm)₹14.08 Lakh
Floor 1110233 sqft (21.61 sqm)₹14.33 Lakh
Floor 1111249 sqft (23.17 sqm)₹15.36 Lakh
Floor 2201738 sqft (68.59 sqm)₹36.37 Lakh
Floor 2203624 sqft (57.94 sqm)₹30.73 Lakh
Floor 2204624 sqft (57.94 sqm)₹30.73 Lakh
Floor 2205632 sqft (58.72 sqm)₹31.14 Lakh
Floor 2206738 sqft (68.59 sqm)₹36.37 Lakh
Floor 2207634 sqft (58.9 sqm)₹31.23 Lakh
Floor 3304624 sqft (57.94 sqm)₹30.73 Lakh
Floor 3305632 sqft (58.72 sqm)₹31.14 Lakh
Floor 3306738 sqft (68.59 sqm)₹36.37 Lakh
Floor 4404624 sqft (57.94 sqm)₹30.73 Lakh
Floor 4406738 sqft (68.59 sqm)₹36.37 Lakh
Floor 5503624 sqft (57.94 sqm)₹30.73 Lakh
Floor 5504624 sqft (57.94 sqm)₹30.73 Lakh
Floor 5506738 sqft (68.59 sqm)₹36.37 Lakh
Floor 6606738 sqft (68.59 sqm)₹36.37 Lakh
Floor 8806738 sqft (68.59 sqm)₹36.37 Lakh
Ground/Floor 02632 sqft (58.72 sqm)₹31.14 Lakh
Ground/Floor 03624 sqft (57.94 sqm)₹30.73 Lakh
Ground/Floor 04624 sqft (57.94 sqm)₹30.73 Lakh
Ground/Floor 05632 sqft (58.72 sqm)₹31.14 Lakh
Ground/Floor 0SHOP-1249 sqft (23.17 sqm)₹15.36 Lakh
Ground/Floor 0SHOP-10233 sqft (21.61 sqm)₹14.33 Lakh
Ground/Floor 0SHOP-11249 sqft (23.17 sqm)₹15.36 Lakh
Ground/Floor 0SHOP-2233 sqft (21.61 sqm)₹14.33 Lakh
Ground/Floor 0SHOP-6238 sqft (22.09 sqm)₹14.64 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9 and 75 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
A1G+97531 Dec 2025

Unit mix on the filing: 53 residential and 22 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202530 Jun 2026As there was a delay in receiving New Sanction Plans from Sanctioning Authority we are applying for Extension of our Project's completion date.

Location, Land & Connectivity

Located at Moshi, New Spine Road, Haveli, Pune, 412105. Per the filed land record, the plot is bounded to the north by Gat No 456 457 459, to the south by 90M DP Road, to the east by 90M DP Road and Gat No 459 Property and to the west by Gat No 452 1 1 2 Property. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)10 km
Baner–Balewadi belt13 km
Pune Junction / city centre14 km
Hinjewadi Rajiv Gandhi IT Park14 km
Kharadi / EON IT Park14 km
Magarpatta / Hadapsar IT17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Moshi

Swastik Twin Tower
possession by Jul 2026 · Swastik Builders
Asha Paradise
possession by Jul 2026 · G T Buildcon
Dhrupi Towers
possession by Jul 2026 · Not Available
RKL Durvankur Jaswand
possession by Jul 2026 · Lunkad Vishwa Developer
Amora Tower
possession by Aug 2026 · Amarnath Creativity
Prime Space
possession by Aug 2026 · Nath Estate

Major developers building in Moshi

Other RERA-registered projects in Pune

Pragati Empire
declared completion Dec 2022 · Prithvi Builders
Pragati Greenwoods
declared completion Jan 2018 · Pragati Construction
Pragati Heights
declared completion Jun 2025 · Pragati Builders And Developers
Pragati Nandanwan
declared completion Jun 2023 · Prithvi Developers
Pragati Serene
declared completion Mar 2026 · Manav Ventures
Pragati Square
declared completion Jun 2021 · Prithvi Infra

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.