Pune/Project record

MahaRERA · the public record

PRIME SPACIO

CHINCHWAD · PRAKASH SAMRUDDHI ASSOCIATES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

28 May 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

28 May 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100022508

Delivery and registration

When is the project declared for completion?

PRIME SPACIO is registered with MahaRERA as P52100022508 and the promoter has declared completion for 28 May 2024.

28 May 2024

declared completion

28months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100022508
Registered on30 Sep 2019
Promoter-declared completion28 May 2024
Current statusCertificate Signed
Against todayabout 28 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PRIME SPACIO record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Prakash Samruddhi Associates is the promoter of record on 100 projects registered with MahaRERA, 16 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

100projects

registered with MahaRERA

16flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PRIME SPACIO in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
PRIME SPACIO1G+831 May 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered28 May 2024DUE TO COVID AND UNAVAILABILITY OF RESOURCES.

Location, Land & Connectivity

Located at CHINCHWAD, DALAVI NAGAR, Haveli, Pune, 411033. Per the filed land record, the plot is bounded to the north by LAYOUT ROAD, to the south by CTS NO 3576, to the east by PLOT NO 33 CTS NO3513 and to the west by PLOT NO 31 CTS NO 3516. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Punawale

Vision ACE Commercial Phase I
possession by Sep 2026 · Vision ACE
7 Plumeria Drive- Phase 3
possession by Sep 2026 · B A Consulting
Austin Arena
possession by Sep 2026 · Austin Real Infra LLP
Shree Heritage
possession by Sep 2026 · Bhakti Venkateshwara Developers
Silveroak C1
Deregistered by MahaRERA · possession by Sep 2026 · SAI Samarttha Properties
Vivanta Next
possession by Sep 2026 · Shree Sonigara Punamiya Developers

Major developers building in Punawale

Other RERA-registered projects in Pune

Prime Tejasya
declared completion Sep 2020 · Prime Priorities
Prime Vastu
possession by Jul 2027 · Prime Construction
Prime Vista
possession by Dec 2029 · Barmecha Darda Associates LLP
Prime Vista Row Houses
possession by Dec 2029 · Barmecha Darda Associates LLP
Primero Casa
declared completion Mar 2018 · Gauri Lively Spaces
Primerose
possession by Mar 2027 · Gurukrupa Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026