MahaRERA Property Intelligence · Pune

QUALITYCONSTRUCTION

P52100016691 · pune · promoter Qualityconstruction

Certificate SignedDue 05 Dec 2021

Delivery & Registration

MahaRERA registrationP52100016691
Registered on05 Jun 2018
Promoter-declared completion05 Dec 2021
Current statusCertificate Signed
Against todayabout 55 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date.

BuildingWingsFloorsDeclared completion
BUILDING A1-01 Oct 2018
BUILDING B1-31 Dec 2017

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
05 Dec 202005 Dec 2021Due to Pandemic the project work could not be completed within time.

Location, Land & Connectivity

Located at pune, shankarseth, Pune City, Pune, 411001. Per the filed land record, the plot is bounded to the north by 4500, to the south by 4500, to the east by 235300 and to the west by 6000. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~109 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park109 km
Baner–Balewadi belt114 km
Pune Junction / city centre125 km
Pune Int'l Airport (Lohegaon)126 km
Kharadi / EON IT Park130 km
Magarpatta / Hadapsar IT130 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ghorpadi

IVY BY Vistaara Homes
possession by Jul 2026 · Vistaarahomes Realty LLP
Profitbay - BT Kawade Road
possession by Aug 2026 · Venturespro Projects LLP
Royal Glen
possession by Sep 2026 · Stargaze Buildcon
Ganga Bhagyoday E Bldg
possession by Dec 2026 · Legends County Landmark Pvt Ltd
Ganga Bhagyoday F Bldg
possession by Dec 2026 · Legends County Landmark Pvt Ltd
Ganga Bhagyoday Tower
possession by Dec 2026 · Legends County Landmark Pvt Ltd

Major developers building in Ghorpadi

Other RERA-registered projects in Pune

Quba Residency
possession by Dec 2028 · Quba Group
QUE 154 A AND B Wing
possession by Sep 2029 · UC Punawale Skyscrapers LLP
QUE 914 Phase I
possession by Dec 2026 · Unique Choice Associates LLP
QUE 914 Phase II
possession by Jun 2027 · Unique Choice Associates LLP
QUE 914 Phase III
possession by Mar 2028 · Unique Choice Associates LLP
Queens Castle
possession by Dec 2027 · Garood Developerzss LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026