R K PRIDE

Punawale · PANKAJ KASHINATH PATIL

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

2units filed as unsoldInventory · 13 September 2026
31 Oct 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Oct 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100009450

Delivery and registration

When is the project declared for completion?

R K PRIDE is registered with MahaRERA as P52100009450 and the promoter has declared completion for 31 Oct 2025.

31 Oct 2025

declared completion

11months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100009450
Registered on22 Aug 2017
Promoter-declared completion31 Oct 2025
Current statusCertificate Signed
Against todayabout 11 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for R K PRIDE record 34 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Pankaj Kashinath Patil is the promoter of record on 69 projects registered with MahaRERA, 13 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

69projects

registered with MahaRERA

13flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

What the filings record, home by home

Read from MahaRERA on 13 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 11 homes carry one, and 2 of the 24 are recorded unsold.

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today.

In R K PRIDE, 0 of the 2 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 2 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
R K PRIDE1G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 4 times, as recorded on the register.

FromExtended toStated reason
as registered01 Aug 2020We have applied for completion certificate and are awaiting for the same.
01 Aug 202031 Dec 2022WE HAVE SUBMIT THE REVISE PLAN IN CORPORATION , SO WE WILL LIKE TO REQUEST FOR PROJECT EXTENSION, THANK YOU
31 Dec 202231 Jul 2024WE WOULD LIKE TO INFORM YOU THAT WE HAVE APPLIED FOR COMPLETION CERTIFICATE AND WAITING THE SAME WE REQUEST YOU TO ALLOW US TO EXTEND THE PROJECT COMPLETION DATE TO 31/07/2024. TH
31 Jul 202431 Oct 2025Resp sir, we will like to inform you that we applied for completion certificate and waiting the same. we request you to allow us to extend the project so that we go for further wor

Location, Land & Connectivity

Located at Punawale, TALERA ROAD, Haveli, Pune, 411033. Per the filed land record, the plot is bounded to the north by GAONTHAN, to the south by PLOT NO 03, to the east by PLOT NO 7 AND ROAD and to the west by PLOT NO 01. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~95 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park95 km
Baner–Balewadi belt100 km
Pune Junction / city centre111 km
Pune Int'l Airport (Lohegaon)112 km
Kharadi / EON IT Park115 km
Magarpatta / Hadapsar IT116 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Pankaj Kashinath Patil is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Punawale

Vision ACE Commercial Phase I
possession by Sep 2026 · Vision ACE
7 Plumeria Drive- Phase 3
possession by Sep 2026 · B A Consulting
Austin Arena
possession by Sep 2026 · Austin Real Infra LLP
Shree Heritage
possession by Sep 2026 · Bhakti Venkateshwara Developers
Silveroak C1
Deregistered by MahaRERA · possession by Sep 2026 · SAI Samarttha Properties
Vivanta Next
possession by Sep 2026 · Shree Sonigara Punamiya Developers

Major developers building in Punawale

Other RERA-registered projects in Pune

R K Residency
declared completion Jun 2022 · R K Developers
R28a Everglades - Phase 2
possession by Jan 2031 · Arys Realtors Private Limited
R48 The Canopy
possession by Dec 2029 · Paranjape Spaces AND Services PVT LTD
R7 - THE Altius
possession by Jan 2030 · Paranjape Spaces AND Services PVT LTD
RA Urbania
declared completion Dec 2025 · Ms Croissance Buildcon
Raahi Kasturi
possession by Dec 2026 · Raahi Yashila

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026