MahaRERA Property Intelligence · Pune

Raja Bahadur 101

P52100028851 · Sangamwadi · promoter Raja Bahadur International

Certificate SignedDue 01 Oct 2028

Delivery & Registration

MahaRERA registrationP52100028851
Registered on05 Apr 2021
Promoter-declared completion01 Oct 2028
Current statusCertificate Signed
Against today27 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Raja Bahadur International is the promoter of record on 12 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
RB1011G+601 Apr 2028

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Sangamwadi , Raja Bahadur Motilal Road , Pune City, Pune, 411001. Per the filed land record, the plot is bounded to the north by Part of Final Plot No 100 and 101 part 1, to the south by Part of Final Plot No 100 and 101 part 1, to the east by Part of Final Plot No 100 and 100 part 1 and to the west by Part of Final Plot No 100 and 101 part 1. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre1 km
Magarpatta / Hadapsar IT6 km
Pune Int'l Airport (Lohegaon)7 km
Kharadi / EON IT Park8 km
Baner–Balewadi belt10 km
Hinjewadi Rajiv Gandhi IT Park15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Raja Bahadur International Ltd. is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Raja Bahadur International Ltd.

Raja Bahadur International Ltd.
FlaggedPune

Other RERA-registered projects in Ghorpadi

IVY BY Vistaara Homes
possession by Jul 2026 · Vistaarahomes Realty LLP
Profitbay - BT Kawade Road
possession by Aug 2026 · Venturespro Projects LLP
Royal Glen
possession by Sep 2026 · Stargaze Buildcon
Ganga Bhagyoday E Bldg
possession by Dec 2026 · Legends County Landmark Pvt Ltd
Ganga Bhagyoday F Bldg
possession by Dec 2026 · Legends County Landmark Pvt Ltd
Ganga Bhagyoday Tower
possession by Dec 2026 · Legends County Landmark Pvt Ltd

Major developers building in Ghorpadi

Other RERA-registered projects in Pune

Rajashree
declared completion Sep 2018 · Pandit Javdekar Associates
Rajashree Elegance
declared completion Jun 2025 · Rajashree Realty
Rajashree Serenity
declared completion Dec 2025 · Rajashree Realtor
Rajashree Simandhar
declared completion Feb 2021 · Rajashree Realty
Rajashri Apartments
possession by Oct 2026 · Omkar Sanjay Thigale
Rajchhaya Heights
possession by Mar 2027 · Enrich Builders

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026