MahaRERA Property Intelligence · Pune

Rise Alta

P52100010096 · Tathawade · promoter Anand Developers

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP52100010096
Registered on24 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
Rise Alta1G+1130 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Honourable C J S D Pune1282016Unready Board
Honourable C J S D Pune14052008Unready Board

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202230 Dec 2020Completion Certificate from Local Authority Awaited.
30 Dec 202230 Jun 2022The Developer has Applied for Completion Certificate with the Pimpri Chinchwad Municipal Corporation. However, the Pimpri Chinchwad Municipal Corporation has called upon the Develo

Location, Land & Connectivity

Located at Tathawade, Near Decathlon Mall, Haveli, Pune, 411033. Per the filed land record, the plot is bounded to the north by Part of Survey Number 56, to the south by Part of Survey Number 56, to the east by Part of Survey Number 56 and to the west by Wakad-Tathawade Road . Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park4 km
Baner–Balewadi belt9 km
Pune Junction / city centre18 km
Pune Int'l Airport (Lohegaon)19 km
Kharadi / EON IT Park22 km
Magarpatta / Hadapsar IT23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every M/s. Anand Developers project & its RERA track record →

Other RERA-registered projects in Punawale

BVM Flora
possession by Jul 2026 · Sunny Naresh Nagdev
Miracle Mathura
possession by Jul 2026 · Miracle Builders And Developers
Sai Aarav
possession by Jul 2026 · Abhijit Prakash Borase
Samarth Paradise
possession by Aug 2026 · Samarth Associates
Isle OF Life - Building B And C
possession by Aug 2026 · R R Ventures
Vision ACE Commercial Phase I
possession by Sep 2026 · Vision ACE

Major developers building in Punawale

Other RERA-registered projects in Pune

Rise Avenue
declared completion Dec 2019 · Rise Realty
Rishabh Avenue Phase I
declared completion Oct 2020 · Vishwamitra AND Rathi
Rising Hills
possession by Aug 2026 · Not Available
Ritika Residency
declared completion Dec 2025 · Waghere Associates
Rituparna Residence
declared completion Nov 2019 · Mitaali Groop
Ritzz City
possession by Jun 2029 · Ritzz Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026