MahaRERA Property Intelligence · Pune

ROSE E MEHAR

P52100000330 · promoter Vinod Premchand Chandwani

Certificate SignedDue 29 Dec 2020

Delivery & Registration

MahaRERA registrationP52100000330
Registered on15 Jul 2017
Promoter-declared completion29 Dec 2020
Current statusCertificate Signed
Against todayabout 67 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Vinod Premchand Chandwani is the promoter of record on 31 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
E1G+729 Jun 2020
COMMERCIAL1G+129 Jun 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Court Senior Division2006222014For Issues

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
29 Dec 202029 Jun 2020The project was sanctioned on 02.11.2018. Earlier only Potential Sanction was obtained. hence the work was not started also no bookings have been taken till date. now the actual co

Location, Land & Connectivity

Located at Haveli, Pune, 411017. Per the filed land record, the plot is bounded to the north by PROPERTY OF NAKHATE, to the south by 18 M WIDE ROAD, to the east by TAMARA PROJECT and to the west by PROPERTY OF KOKANE. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~111 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park111 km
Baner–Balewadi belt117 km
Pune Int'l Airport (Lohegaon)126 km
Pune Junction / city centre126 km
Kharadi / EON IT Park130 km
Magarpatta / Hadapsar IT132 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Vinod Premchand Chandwani is the promoter on 19 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Vinod Premchand Chandwani project & its RERA track record →

Other flagged projects by Vinod Premchand Chandwani

Vinod Premchand Chandwani
Not filing quarterly progress reportsPune
Vinod Premchand Chandwani
FlaggedPune
Vinod Premchand Chandwani
FlaggedPune
Vinod Premchand Chandwani
FlaggedPune
Vinod Premchand Chandwani
FlaggedPune
Vinod Premchand Chandwani
FlaggedPune

Other RERA-registered projects in Rahatani

Adi Amma Insperia
possession by Jul 2026 · J N Realty And Homes
Devkamal Heights
possession by Oct 2026 · MRS Kamal Devram Hole
KK Mangalam Emerald
possession by Oct 2026 · Shah Associates & Properties
AUM Vertex
possession by Dec 2026 · Aum Buildcon
KK Capitol
possession by Dec 2026 · Shah AND Associates
Tamara
possession by Dec 2026 · Goldfinger Kataria Urban Developments

Major developers building in Rahatani

Other RERA-registered projects in Pune

Rose Galaxy
declared completion Mar 2026 · Rose Dream Developers
Rose Gardenia
possession by Sep 2026 · Rose Dream Developers
Rose Gardenia Phase II
possession by Sep 2026 · Rose Dream Developers
Rose Mansion
declared completion Dec 2020 · Vinod Premchand Chandwani
Rose Parade - Wing C1 And C2
declared completion Jun 2026 · Ankit Landmarks Private Limited
Rose Paradise
possession by Jul 2028 · Tasneem Construction

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026