Royal Krushankunj Residences

NEXT TO JAIN TEMPLE · AVANEESH INFRA.

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

18 Jul 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

18 Jul 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100015277

Delivery and registration

When is the project declared for completion?

Royal Krushankunj Residences is registered with MahaRERA as P52100015277 and the promoter has declared completion for 18 Jul 2022.

18 Jul 2022

declared completion

50months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100015277
Registered on12 Feb 2018
Promoter-declared completion18 Jul 2022
Current statusCertificate Signed
Against todayabout 50 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Royal Krushankunj Residences record 19 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 19 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Avaneesh Infra is the promoter of record on 4 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Royal Krushankunj Residences in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
Royal Krushankunj Residences WING B1G+718 Jan 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered18 Jul 2022We had reduced construction pace due to pandemic and slag in sales / market condition

Location, Land & Connectivity

Located at NEXT TO JAIN TEMPLE, NIRA BARAMATI ROAD, Purandhar, Pune, 412102. Per the filed land record, the plot is bounded to the north by 24 Meter wide road, to the south by NEXT TO CTS422, to the east by NEXT TO CTS 441 and to the west by NEXT TO CTS483. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~56 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Magarpatta / Hadapsar IT56 km
Kharadi / EON IT Park59 km
Pune Junction / city centre61 km
Pune Int'l Airport (Lohegaon)63 km
Baner–Balewadi belt70 km
Hinjewadi Rajiv Gandhi IT Park75 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Avaneesh Infra. is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Avaneesh Infra.

Avaneesh Infra.
Past its declared completion datePune

Other RERA-registered projects in Nimbut

VTB Landmark
possession by Dec 2026 · Tanoj Digambar Borate
Shree Sadhguru Residencey
Not filing quarterly progress reports · declared completion Apr 2025 · Vijayratna Developers
Neera City Centre
Past its declared completion date · declared completion Jul 2023 · Avaneesh Infra.
Nisarg Human Park
Past its declared completion date · declared completion Aug 2019 · Anil Vasant Sorate

Other RERA-registered projects in Pune

Royal Oak
possession by Dec 2026 · Lifestyle Developments
Royal Orchid
declared completion Jul 2023 · Royal Square Developers
Royal Orchid Residency
declared completion Dec 2025 · Balaji Developers
Royal Palm
declared completion Dec 2021 · Vaishali Developers & Builders
Royal Panchwati
possession by Jun 2027 · Royal Developers
Royal Paradise
declared completion Dec 2023 · Vineet Builders AND Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026