MahaRERA Property Intelligence · Pune

Saarrthi Shivalik

P52100014200 · Kothrud · promoter Siddharth Real Ventures

Certificate SignedDue 30 Sep 2020

Delivery & Registration

MahaRERA registrationP52100014200
Registered on14 Nov 2017
Promoter-declared completion30 Sep 2020
Current statusCertificate Signed
Against todayabout 70 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Siddharth Real Ventures is the promoter of record on 18 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
Saarrthi Shivalik1G+1531 Mar 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court3602003Pending For Admission Against One Flat Number Four Zero Three Only

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Sep 202031 Mar 2021Part completion recieved for the building. Due to force majeure and covid the project could not be completed in entirety.

Location, Land & Connectivity

Located at Kothrud, Kothrud, Pune City, Pune, 411038. Per the filed land record, the plot is bounded to the north by Plot No 15 and 16, to the south by Karve road, to the east by Plot no 6 and to the west by Plot no 9. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre7 km
Baner–Balewadi belt8 km
Magarpatta / Hadapsar IT11 km
Hinjewadi Rajiv Gandhi IT Park13 km
Pune Int'l Airport (Lohegaon)14 km
Kharadi / EON IT Park14 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Siddharth Real Ventures Limited Liability Partnership is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Siddharth Real Ventures Limited Liability Par

Siddharth Real Ventures Limited Liability Partnership
FlaggedPune

Other RERA-registered projects in Kothrud

Umed
possession by Jul 2026 · Runwal Realtors Pvt Ltd
Chandra Apartment
possession by Aug 2026 · Deshpande Landmark Private Limited
Keshar
possession by Aug 2026 · Badhekar Properties
Tungabhadra CO OP HSG SOC
possession by Aug 2026 · Not Available
Arunali
possession by Sep 2026 · Badhekar Properties
Guruvaibhav CO-Op.housing Society Limited
possession by Sep 2026 · Shreepad Associates

Major developers building in Kothrud

Other RERA-registered projects in Pune

Saarrthi Skybay
declared completion Nov 2020 · Siddharth Properties
Saarrthi Skybay II
declared completion Sep 2025 · Siddharth Properties
Saarrthi Skybay III
possession by Dec 2026 · Siddharth Properties
Saarrthi Skybizz
possession by Mar 2027 · Siddharth Properties
Saarrthi Supremus
possession by Dec 2027 · Siddharth Properties
Saarrthi Swadesh
declared completion Jul 2024 · Siddharth Properties

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026