Pune/Project record

MahaRERA · the public record

SHANTAI PARK

Pune · SAMARTTHA LANDMARK

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100006559

Delivery and registration

When is the project declared for completion?

SHANTAI PARK is registered with MahaRERA as P52100006559 and the promoter has declared completion for 31 Dec 2022.

31 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100006559
Registered on14 Aug 2017
Promoter-declared completion31 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHANTAI PARK record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Samarttha Landmark is the promoter of record on 18 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

18projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHANTAI PARK in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
SHANTAI PARK1G+729 Jan 2020

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for SHANTAI PARK, with orders passed in 5 of them.

5complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000001149805/05/2018SEEMA PRITESH DUGAD vs SAMARTTHA LANDMARKorder passed
CC00500000003355120/10/2019Mr.Pritesh Prakash Dugad vs Samarttha Landmark, a registered partnership firm through its partners Mr.Mahesh Hiraman Barneorder passed
CC00500000003355420/10/2019Mrs.Seema Pritesh Dugad vs Samarttha Landmark a registred partnership firm through its partnersorder passed
CC00500000009572901/07/2021MR PRITESH PRAKASH DUGAD vs samarttha landmark a regi partnership firm though its partnersorder passed
CC00500000002331117/01/2020UMESH KASHINATH JOSHI vs SAMARTTHA LANDMARKorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered29 Jan 20202There was procedural tussle regarding plot and that is because of change of development plan by Development Authority which leads cutting of some part of our plot for City Infrast
29 Jan 202031 Dec 2021The construction work of the existing buildings has been completed and some of the amenities/finishing work are remaining which we as a Promoter undertakes to expedite. We, the Pr
31 Dec 202131 Dec 2022due to revise sanction plan

Location, Land & Connectivity

Located at Mulshi, Pune, 411033. Per the filed land record, the plot is bounded to the north by CTS NO 6260, to the south by ROAD, to the east by CTS 2417 and to the west by NALA. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~114 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park114 km
Baner–Balewadi belt119 km
Pune Junction / city centre129 km
Pune Int'l Airport (Lohegaon)130 km
Kharadi / EON IT Park134 km
Magarpatta / Hadapsar IT135 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Punawale

Vision ACE Commercial Phase I
possession by Sep 2026 · Vision ACE
7 Plumeria Drive- Phase 3
possession by Sep 2026 · B A Consulting
Austin Arena
possession by Sep 2026 · Austin Real Infra LLP
Shree Heritage
possession by Sep 2026 · Bhakti Venkateshwara Developers
Silveroak C1
Deregistered by MahaRERA · possession by Sep 2026 · SAI Samarttha Properties
Vivanta Next
possession by Sep 2026 · Shree Sonigara Punamiya Developers

Major developers building in Punawale

Other RERA-registered projects in Pune

Shantais Divine Vastu
possession by Dec 2026 · Mahalaxmi Developers
Shantanu Height
possession by Dec 2026 · Shashidhar Singh
Shanti Anand
declared completion Dec 2025 · Sankalp Promoters
Shanti Complex Building C
declared completion Dec 2024 · Tejus Builders AND Developers
Shanti Krupa
declared completion Oct 2023 · Chandranchal Properties
Shanti Towers
declared completion Dec 2025 · Bora Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026