Pune/Project record

MahaRERA · the public record

SHIVNERI

MUNDHAWA · SAHYADRI CONSTRUCTION

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100020865

Delivery and registration

When is the project declared for completion?

SHIVNERI is registered with MahaRERA as P52100020865 and the promoter has declared completion for 31 Dec 2023.

31 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100020865
Registered on15 May 2019
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHIVNERI record 19 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 19 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sahyadri Construction is the promoter of record on 45 projects registered with MahaRERA, 5 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

45projects

registered with MahaRERA

5flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHIVNERI in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
SHIVNERI1G+403 Oct 2021

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for SHIVNERI, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000025909902/07/2023Tushar Machchhindra Pawar vs Sahyadri Constructionsorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2023Project is delayed due to revision in sanctioned plan and increased in no of flats.
31 Mar 202331 Dec 2023Project is delaying due to some technical changes.

Location, Land & Connectivity

Located at MUNDHAWA, MUNDHAWA, Haveli, Pune, 411036. Per the filed land record, the plot is bounded to the north by CTS NO 1 AND ROAD, to the south by CTS NO 5, to the east by ROAD and to the west by CTS NO 2. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sahyadri Construction is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Mundhwa

Casa Elanza
possession by Sep 2026 · Parmaz Green Realty LLP
Platinum Capital Office - Phase I
possession by Sep 2026 · A Advani Properties LLP
The Golden Bell
Not filing quarterly progress reports · possession by Dec 2026 · Panchshil Hotels Pvt Ltd
ACE Villas
possession by Dec 2026 · Jhamtani Realty Private Limited
Anandtara Iris Residences Phase I
possession by Dec 2026 · Anandtara Infrastructure
Anandtara Iris Residences Phase II
possession by Dec 2026 · Anandtara Infrastructure

Major developers building in Mundhwa

Other RERA-registered projects in Pune

Shivom Regency
declared completion Mar 2020 · Space Builders & Developers
Shivpadma Residency
declared completion Mar 2020 · N B Properties
Shivpriya Residency
declared completion Dec 2024 · OM Gurudev Promoters Builders AND Contra
Shivram Heights
declared completion Sep 2023 · Royal Builders
Shivranjani - A
declared completion Jul 2019 · Kjrealtors
Shivratna
declared completion Jul 2026 · Mr Rajan Vishram Palekar

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026