Pune/Project record

MahaRERA · the public record

SHREEKRUSHNA-LEELA PARK

Nashik · Sunpra Sheltors India Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Mar 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100009191

Delivery and registration

When is the project declared for completion?

SHREEKRUSHNA-LEELA PARK is registered with MahaRERA as P52100009191 and the promoter has declared completion for 30 Mar 2022.

30 Mar 2022

declared completion

54months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100009191
Registered on22 Aug 2017
Promoter-declared completion30 Mar 2022
Current statusCertificate Signed
Against todayabout 54 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREEKRUSHNA-LEELA PARK record 19 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 19 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sunpra Sheltors India is the promoter of record on 9 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

9projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHREEKRUSHNA-LEELA PARK in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
BLDG A1G+431 Mar 2021
BLDG B1G+431 Mar 2021
BLDG C1G+431 Mar 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Sinnar, Nashik, 410501. Per the filed land record, the plot is bounded to the north by ROAD, to the south by 1031, to the east by 1025 and to the west by 1027. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~114 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park114 km
Baner–Balewadi belt119 km
Pune Junction / city centre129 km
Pune Int'l Airport (Lohegaon)130 km
Kharadi / EON IT Park134 km
Magarpatta / Hadapsar IT135 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Chakan

Vallabh Heights
possession by Sep 2026 · G R Developers
Shree Samarth Shrushti
possession by Sep 2026 · Jagdamba Developers
Swapnapurti Heights
Not filing quarterly progress reports · possession by Oct 2026 · B R Developers
Richmond
possession by Oct 2026 · Coral Shubh Builders
Mungase Towers
possession by Dec 2026 · Mr Santosh Vasudev Mungase
Chakan High Street
possession by Dec 2026 · Chakan Business HUB LLP

Major developers building in Chakan

Other RERA-registered projects in Pune

Shreekunj Shree
declared completion Dec 2024 · Gokhale Shelters LLP
Shreekunja
declared completion Jul 2025 · Badhekar Properties
Shreenagari
declared completion Dec 2024 · Sharda Sarla Builders
Shreenath Market City
possession by Dec 2028 · Ozone Infrastructure
Shreenath Residency
declared completion Apr 2026 · Chandrakant Gulab Jamdade
Shreenath Residency
declared completion Jun 2024 · Sawai Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026