Pune/Project record

MahaRERA · the public record

SHREERAM EUPHORIA

LOHEGAON · RR REALTY

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

32units filed as unsoldInventory · 18 September 2026
31 Mar 2028declared completionMahaRERA registration · read 12 Jul 2026
130registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100045418

Delivery and registration

When is the project declared for completion?

SHREERAM EUPHORIA is registered with MahaRERA as P52100045418 and the promoter has declared completion for 31 Mar 2028.

31 Mar 2028

declared completion

18months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100045418
Registered on18 May 2022
Promoter-declared completion31 Mar 2028
Current statusCertificate Signed
Against today18 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREERAM EUPHORIA record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Sales

How much has actually been sold?

In SHREERAM EUPHORIA, 38 of 84 homes filed with MahaRERA are recorded as sold or booked, about 45%, and 46 remain available.

45%sold

38 of 84 homes

₹20.87 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹17.26 Cr (about 83%) is recorded as collected and ₹3.61 Cr as receivable. The project registers 130 homes in total, while this sold/unsold inventory filing covers 84 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 38 registered agreements, the effective carpet rate is ₹6,988/sqft, with eight in ten falling between ₹6,368 and ₹9,054 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 43 owner/investor-held and 3 not for sale.

What the filings record, home by home

Read from MahaRERA on 18 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 49 homes carry one, and 32 of the 154 are recorded unsold. Since we started watching this ledger, 8 homes have moved out of the unsold list, most recently on 18 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
A-207901 sqftRs 67.59 lakh typical, over Rs 61.25 lakh to Rs 67.59 lakh3 filed on this stack, floors 4–8

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In SHREERAM EUPHORIA, 11 of the 32 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 31 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13 and 130 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Wing A1G+1381-
Wing B1G+549-

Unit mix on the filing: 102 residential and 28 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2028We would like to bring to your kind attention that Wing B has been incorporated as an additional component in the ongoing project. The Commencement Certificate for Wing B has been

Location, Land & Connectivity

Located at LOHEGAON, LOHEGAON, Haveli, Pune, 411047. Per the filed land record, the plot is bounded to the north by SATHE VASTI LOHEGAON ROAD, to the south by ADJOINING LAND OF VISHNU SATHE OF SR NO 276, to the east by ADJOINING LAND OF SR NO 276 and to the west by ADJOINING LAND OF SR NO 276. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~32 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park32 km
Baner–Balewadi belt32 km
Pune Junction / city centre39 km
Magarpatta / Hadapsar IT43 km
Pune Int'l Airport (Lohegaon)46 km
Kharadi / EON IT Park46 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Lohegaon

Aayush Exotica
possession by Sep 2026 · Aayush Properties
Chandan Heritage
possession by Sep 2026 · City Developers
Youthika
possession by Oct 2026 · Krushnarang Group
Pankaj Aasmaan Phase V
possession by Dec 2026 · Pankaj Developers
Aayush Wisteria
possession by Dec 2026 · Pritam Kantilal Khandve
Divine Garden Phase 1
possession by Dec 2026 · Shriram Associates

Major developers building in Lohegaon

Other RERA-registered projects in Pune

Shreeram Kalash Phase 2 Commercial
declared completion Oct 2022 · Krishna Group
Shreeram Shivalay East
declared completion Jun 2026 · Rohit Skylines
Shreeram Shivalay West
declared completion Mar 2026 · Rohit Skyline
Shreeram Swapnpurti
declared completion Aug 2023 · Ram Budget Homes
Shreeram Tradecon
declared completion Dec 2018 · Shreeramtradecon
Shreeram Tradecon
declared completion Oct 2025 · Shreeram Tradecon

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026