Pune/Project record

MahaRERA · the public record

Shreeram Swapnpurti

Pune · Ram Budget Homes

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

01 Aug 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

01 Aug 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100013265

Delivery and registration

When is the project declared for completion?

Shreeram Swapnpurti is registered with MahaRERA as P52100013265 and the promoter has declared completion for 01 Aug 2023.

01 Aug 2023

declared completion

37months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100013265
Registered on21 Sep 2017
Promoter-declared completion01 Aug 2023
Current statusCertificate Signed
Against todayabout 37 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Shreeram Swapnpurti record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 25 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Ram Budget Homes is the promoter of record on 2 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Shreeram Swapnpurti in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Shreeram Swapnpurti1G+501 Feb 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Haveli, Pune, 412308. Per the filed land record, the plot is bounded to the north by 69, to the south by 69, to the east by 69 68 and to the west by Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~84 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park84 km
Baner–Balewadi belt89 km
Pune Junction / city centre100 km
Pune Int'l Airport (Lohegaon)101 km
Kharadi / EON IT Park105 km
Magarpatta / Hadapsar IT105 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Fursungi

Casalino Towers Phase 3
possession by Oct 2026 · Sai Siddhi Promoters & Builders
Green Hive Plus Wing A4
possession by Dec 2026 · Ram India Shelters
THE Mpire Building E
possession by Dec 2026 · AGN Venture
Vandan Vihar
possession by Jun 2027 · GVN Developers PVT LTD
AGS Complex
possession by Sep 2027 · AGS Properties
Pacific Tower
possession by Sep 2027 · Chaitanya Developers

Major developers building in Fursungi

Other RERA-registered projects in Pune

Shreeram Tradecon
declared completion Dec 2018 · Shreeramtradecon
Shreeram Tradecon
declared completion Oct 2025 · Shreeram Tradecon
Shrees Kadam Paradise
possession by Dec 2029 · Narendra Maganlal Solanki
Shreesamarth Residency
declared completion Dec 2021 · Dilip Kaluram More
Shreesha Icon
possession by Jul 2029 · Imperial Buildcon
Shreetej Apartments
possession by Mar 2027 · Aster Trisha Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026