MahaRERA Property Intelligence · Pune

Siddhi Villa

P52100006879 · promoter Sankalp Associates

Certificate SignedDue 15 Aug 2019

Delivery & Registration

MahaRERA registrationP52100006879
Registered on16 Aug 2017
Promoter-declared completion15 Aug 2019
Current statusCertificate Signed
Against todayabout 83 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sankalp Associates is the promoter of record on 85 projects, of which 9 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
Siddhi Villa1G+12-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Haveli, Pune, 412101. Per the filed land record, the plot is bounded to the north by 1, to the south by 5, to the east by 3 and to the west by 3. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~105 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park105 km
Baner–Balewadi belt111 km
Pune Junction / city centre121 km
Pune Int'l Airport (Lohegaon)121 km
Kharadi / EON IT Park125 km
Magarpatta / Hadapsar IT126 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ravet

Shivratna
possession by Jul 2026 · Mr Rajan Vishram Palekar
Glorious Tathastu
possession by Jul 2026 · Glorious Buildcon
Aqua Life
possession by Aug 2026 · Legacy Lifespaces LLP
City ONE Skyve
possession by Sep 2026 · Shree SAI Capital
Godrej Carnival
possession by Sep 2026 · Godrej Skyline Developers Limited
Godrej Nurture
possession by Sep 2026 · Godrej Skyline Developers Limited

Major developers building in Ravet

Other RERA-registered projects in Pune

Siddhi Vinayak Residency
declared completion Jun 2021 · Shree Siddhivinayak Developers
Siddhichandrabhaga Heights
declared completion Dec 2025 · Bharat Vastimal Solanki
Siddhigiri
possession by Dec 2026 · Anand Homes
Siddhis Sapphire Homes
possession by Dec 2027 · Siddhis Venture
Siddhivinayak
declared completion Mar 2024 · Shree Ashtavinayak Developers
Siddhivinayak
declared completion Dec 2024 · Kedar Vikasrao Deshpande

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026