MahaRERA · the public record
SIGMA CENTURIA PHASE II
FURSUNGI · SIGMA2 BUILDZONE LLP
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 02 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Dec 2030
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 02 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · PR1260002502599
Delivery and registration
When is the project declared for completion?
SIGMA CENTURIA PHASE II is registered with MahaRERA as PR1260002502599 and the promoter has declared completion for 30 Dec 2030.
30 Dec 2030
declared completion
51months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 02 Jul 2026
| MahaRERA registration | PR1260002502599 |
| Registered on | 04 Mar 2026 |
| Promoter-declared completion | 30 Dec 2030 |
| Current status | Certificate Signed |
| Against today | 51 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SIGMA CENTURIA PHASE II record 1 quarterly progress report since registration.
1quarterly filing
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 02 Jul 2026
- Filing progress reports — 1 quarterly progress report on record since registration, with no current default.
Construction
How much construction cost has been reported?
In SIGMA CENTURIA PHASE II, ₹2.70 Cr of a declared ₹20.57 Cr estimated project cost is reported as incurred, about 13.1%, as at the last certified filing with MahaRERA.
13.1%
₹2.70 Cr
of ₹20.57 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 02 Jul 2026
Sales
How much has actually been sold?
In SIGMA CENTURIA PHASE II, 14 of 87 homes filed with MahaRERA are recorded as sold or booked, about 16%, and 73 remain available.
16%sold
14 of 87 homes
₹1.92 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹76.18 Lakh (about 40%) is recorded as collected and ₹1.26 Cr as receivable.
Source · MahaRERA sold/unsold inventory filing · read 02 Jul 2026
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for SIGMA CENTURIA PHASE II in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 September 2026
What the filings record, home by home
Read from MahaRERA on 12 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 4 homes carry one, and 73 of the 87 are recorded unsold.
Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:
| Home | Carpet | Filed for the same home on other floors | Based on |
|---|---|---|---|
| 1001 | 618 sqft | Rs 47.50 lakh typical, over Rs 44.00 lakh to Rs 52.53 lakh | 4 filed at this size |
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11 and 87 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| Tower 1 | 1 | G+11 | 87 | - |
Unit mix on the filing: 87 residential.
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Location, Land & Connectivity
Located at FURSUNGI, PLOT NO 2 S NO. 204/4, 5, 6, 7, Pune City, Pune, 412308. Per the filed land record, the plot is bounded to the north by BY PLOT NO 1 AND BY EXITING ROAD AND SR.NO 205, to the south by BY AMENITY SPACE FROM OUT OF SAID PLOT NO 2, to the east by EXISTING ROAD AND SR.NO 205 and to the west by BY LAND BEARING SR.NO 204 HISSA NO 9. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Magarpatta / Hadapsar IT | 8 km |
| Kharadi / EON IT Park | 11 km |
| Pune Junction / city centre | 13 km |
| Pune Int'l Airport (Lohegaon) | 15 km |
| Baner–Balewadi belt | 23 km |
| Hinjewadi Rajiv Gandhi IT Park | 29 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.