Pune/Project record

MahaRERA · the public record

SingaPune Ph 3

Charoli Budruk · Xrbia Mirth Properties LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

902units filed as unsoldInventory · 17 September 2026
30 Dec 2028declared completionMahaRERA registration · read 12 Jul 2026
902registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100021752

Delivery and registration

When is the project declared for completion?

SingaPune Ph 3 is registered with MahaRERA as P52100021752 and the promoter has declared completion for 30 Dec 2028.

30 Dec 2028

declared completion

27months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100021752
Registered on23 Jul 2019
Promoter-declared completion30 Dec 2028
Current statusCertificate Signed
Against today27 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SingaPune Ph 3 record 31 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Xrbia Mirth Properties is the promoter of record on 28 projects registered with MahaRERA, 17 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

28projects

registered with MahaRERA

17flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In SingaPune Ph 3, 0 of 902 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 902 remain available.

0%sold

0 of 902 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SingaPune Ph 3 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 17 September 2026

What the filings record, home by home

Read from MahaRERA on 17 September 2026

No home in SingaPune Ph 3 carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 902 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 5,010 a sq ft typical, over Rs 5,010 to Rs 5,011.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 902 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 902 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12 and 902 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
B31G+1233631 Dec 2027
B41G+1127831 Dec 2027
C41G+1214431 Dec 2027
C51G+1214431 Dec 2027

Unit mix on the filing: 888 residential and 14 non-residential (shops/offices).

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for SingaPune Ph 3, with orders passed in 4 of them.

5complaints

4with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000008544713/04/2021ARVIND MANOR vs XRBIA DEVELOPERS PVT LTDorder passed
CC00500000011688201/04/2022Mohammad Iqbal Pathan vs Xrbia Mirth Propertiesorder passed
CC1240072410/11/2024Sanjo Geo Mathew vs Xrbia Mirth Properties LLPorder passed
CC1240083520/11/2024Sunil Chensukhlal Kathed vs Xrbia Mirth Properties LLPorder passed
CC1240104405/12/2024ROHIT SHANKARLAL SANTANI vs Xrbia Mirth Properties LLPpending / no order on file

Location, Land & Connectivity

Located at Charoli Budruk, Proposed DP Road, Pune City, Pune, 412105. Per the filed land record, the plot is bounded to the north by Sr No 307 Sr No 308 and Road, to the south by Sr No 310, to the east by Sr No 309 Part and to the west by Sr No 305 and Sr No 309 Part. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~32 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park32 km
Baner–Balewadi belt32 km
Pune Junction / city centre39 km
Magarpatta / Hadapsar IT44 km
Pune Int'l Airport (Lohegaon)46 km
Kharadi / EON IT Park46 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Xrbia Mirth Properties LLP is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Xrbia Mirth Properties LLP

Xrbia Mirth Properties LLP
FlaggedPune
Xrbia Mirth Properties LLP
FlaggedPune

Other RERA-registered projects in Moshi

Ideal Avenue
possession by Sep 2026 · Ideal Builders
Fortune Vedas Phase II
Not filing quarterly progress reports · possession by Sep 2026 · Fortune Vastusilpa Developers LLP
Gulmohar 24
possession by Sep 2026 · Royal Gulmohar Reality
Krishnai Residency
possession by Sep 2026 · Vastu Buildcon
Omkar Residency
possession by Sep 2026 · Prerna Group
Town Square
possession by Sep 2026 · Krupasindhu Developers

Major developers building in Moshi

Other RERA-registered projects in Pune

Singh CHS
possession by Dec 2028 · Chaphalkar Karandikar Developers
Sinhagad City
declared completion Dec 2023 · Prime Developers
Sinhagad Darshan
declared completion Jun 2024 · Jayesh Pravin Jain
Sitangan Residency
declared completion May 2025 · Kalbhor Associates LLP
Siya Corner
declared completion Jun 2024 · S S Developers
Siyona Phase - II
possession by Mar 2029 · Pethkar Projects

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.