Pune/Project record

MahaRERA · the public record

SQUARE INFINITY

Pune · Square Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100007080

Delivery and registration

When is the project declared for completion?

SQUARE INFINITY is registered with MahaRERA as P52100007080 and the promoter has declared completion for 31 Jul 2022.

31 Jul 2022

declared completion

50months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100007080
Registered on17 Aug 2017
Promoter-declared completion31 Jul 2022
Current statusCertificate Signed
Against todayabout 50 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SQUARE INFINITY record 21 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Square Developers is the promoter of record on 194 projects registered with MahaRERA, 18 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

194projects

registered with MahaRERA

18flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SQUARE INFINITY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
SQUARE INFINITY1G+731 Jul 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Jan 2022On Account of varied reasons at different points of time during the tenure of the project such as: a. Non- availability or limited supply of steel, other building material, wate

Location, Land & Connectivity

Located at Haveli, Pune, 412308. Per the filed land record, the plot is bounded to the north by 24 METRE ROAD, to the south by SR NO 153 PART, to the east by 7-50 MTR ROAD and to the west by SR NO 153 PART. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~105 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park105 km
Baner–Balewadi belt110 km
Pune Junction / city centre120 km
Pune Int'l Airport (Lohegaon)121 km
Kharadi / EON IT Park125 km
Magarpatta / Hadapsar IT126 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Fursungi

Casalino Towers Phase 3
possession by Oct 2026 · Sai Siddhi Promoters & Builders
Green Hive Plus Wing A4
possession by Dec 2026 · Ram India Shelters
THE Mpire Building E
possession by Dec 2026 · AGN Venture
Vandan Vihar
possession by Jun 2027 · GVN Developers PVT LTD
AGS Complex
possession by Sep 2027 · AGS Properties
Pacific Tower
possession by Sep 2027 · Chaitanya Developers

Major developers building in Fursungi

Other RERA-registered projects in Pune

Square One
declared completion Jun 2026 · Kokane - Waghere Associates
Square One
possession by Dec 2028 · A Square Developer
SR House
possession by May 2031 · S R Buildpro Icon LLP
SRI Kubera Associates Daund
declared completion Mar 2022 · Srikuberaassociatess
SRI SAI Chaithanya
declared completion Jan 2021 · Perinjelil Madhusoodanan Pillai
SRI Sarswati
declared completion Jun 2025 · Yogesh Sharad Gavankar

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026