MahaRERA Property Intelligence · Pune
P52100052664 · ERANDWANE · promoter Tejraj Profile Builders
| MahaRERA registration | P52100052664 |
| Registered on | 15 Sep 2023 |
| Promoter-declared completion | 24 Dec 2026 |
| Current status | Certificate Signed |
| Against today | 5 months to the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Tejraj Profile Builders is the promoter of record on 10 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
MahaRERA's cost filing puts construction at ~73.9% of the estimated project cost incurred as of the last certificate (₹9.39 Cr spent against a ₹12.71 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.
Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.
Of 16 homes filed with MahaRERA, 12 are sold/booked and 4 remain available (~75% sold) — selling steadily. Buyers have committed ₹26.56 Cr in agreement value so far. Of that, ₹22.08 Cr (~83%) is already collected, ₹4.48 Cr receivable — a read on how far along these sales really are. Note: the project registers 29 homes in total, but this sold/unsold inventory filing covers only 16 of them — the other 13 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.
What buyers actually paid: across 12 registered agreements, the effective carpet rate is ₹18,844/sqft (typical range ₹18,521–₹20,852) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.
The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:
| Floor | Unit | Carpet | Reckoner value |
|---|---|---|---|
| Floor 1 | 101 | 934 sqft (86.77 sqm) | ₹1.32 Cr |
| Floor 1 | 102 | 907 sqft (84.26 sqm) | ₹1.28 Cr |
| Floor 2 | 201 | 934 sqft (86.77 sqm) | ₹1.32 Cr |
| Floor 2 | 202 | 907 sqft (84.26 sqm) | ₹1.28 Cr |
⚠ The inventory filing also declares: 13 not for sale. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4 and 29 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| TEJ NAVYA | 1 | G+4 | 29 | - |
Unit mix on the filing: 29 residential.
No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.
The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 24 Dec 2025 | 24 Dec 2026 | The construction work of the said project is substantially completed, and only certain infrastructure-related works are pending. Therefore, we will be requiring extra time to compl |
Located at ERANDWANE, ERANDWANE, Pune City, Pune, 411038. Per the filed land record, the plot is bounded to the north by SURVEY NO 36 7 PLOT NO 1, to the south by SURVEY NO 36 7 PLOT NO 3, to the east by CUMMINS and to the west by COLONY ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Pune Junction / city centre | 2 km |
| Magarpatta / Hadapsar IT | 7 km |
| Kharadi / EON IT Park | 9 km |
| Baner–Balewadi belt | 9 km |
| Pune Int'l Airport (Lohegaon) | 10 km |
| Hinjewadi Rajiv Gandhi IT Park | 15 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Free · Watch this project
We'll email you when this project's RERA record changes.
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026