TULJAI RESIDENCY

P52100018818 · JAMBE · promoter Tuljabhavani Developers

Certificate SignedDue 30 Jun 2024

Delivery & Registration

MahaRERA registrationP52100018818
Registered on05 Dec 2018
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 25 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Tuljabhavani Developers is the promoter of record on 2 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
BUILDING B1G+6-
BUILDING A1G+5-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202230 Jun 2024We , the Promoter of TULJAI RESIDENCY , were not ableto upload Form-4 due to non-receipt of Occupancy Certificate.Due to impact of Covid -19 & subsequent unavailabilityof skilled l

Location, Land & Connectivity

Located at JAMBE, JAMBE ROAD, Mawal, Pune, 411033. Per the filed land record, the plot is bounded to the north by 30 M WIDE PROP RP ROAD, to the south by S NO 145 P, to the east by S NO 144 and to the west by S NO 145 P. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Punawale

BVM Flora
possession by Jul 2026 · Sunny Naresh Nagdev
Miracle Mathura
possession by Jul 2026 · Miracle Builders And Developers
Sai Aarav
possession by Jul 2026 · Abhijit Prakash Borase
Samarth Paradise
possession by Aug 2026 · Samarth Associates
Isle OF Life - Building B And C
possession by Aug 2026 · R R Ventures
Vision ACE Commercial Phase I
possession by Sep 2026 · Vision ACE

Major developers building in Punawale

Other RERA-registered projects in Pune

Tulsai Heights
declared completion Dec 2017 · Sachin Kishanrao Padwal
Tulshi Vrindavan Market
declared completion Nov 2024 · Riddhi Siddhi Market
Tulsi 54
declared completion May 2025 · Tulsidas Shamrao Patil
Tulsi Aangan
declared completion Jun 2018 · Tushar Narayan Patil
Tulsi Aangan
possession by Dec 2029 · Yashodha Rise Group
Tulsi Angan-2 D Wing And E Wing
declared completion Jun 2024 · D J Buildcon

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026