Vertical Oriana Phase II

P52100003699 · Mundhwa · promoter Vertical Infra

Certificate SignedDue 30 Jun 2019

Delivery & Registration

MahaRERA registrationP52100003699
Registered on06 Aug 2017
Promoter-declared completion30 Jun 2019
Current statusCertificate Signed
Against todayabout 85 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Vertical Infra is the promoter of record on 7 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
Building B1G+1717 May 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Mundhwa, Keshavnagar , Pune City, Pune, 411036. Per the filed land record, the plot is bounded to the north by By land of survey no-6 Mudhwa, to the south by By Road, to the east by By land of survey no-6 Mudhwa and to the west by By land of survey no-7 Mudhwa. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~105 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park105 km
Baner–Balewadi belt110 km
Pune Junction / city centre121 km
Pune Int'l Airport (Lohegaon)123 km
Kharadi / EON IT Park126 km
Magarpatta / Hadapsar IT126 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Vertical Infra is the promoter on 5 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Vertical Infra

Vertical Infra
Past its declared completion datePune

Other RERA-registered projects in Mundhwa

Moonstone
possession by Aug 2026 · Swamiji Developers
Matoshree Pride
Not filing quarterly progress reports · possession by Aug 2026 · Devidas Suresh Bhat
Shubh Evan C1 Wing
possession by Aug 2026 · Kalash Enterprises
Casa Elanza
possession by Sep 2026 · Parmaz Green Realty LLP
Platinum Capital Office - Phase I
possession by Sep 2026 · A Advani Properties LLP
The Golden Bell
Not filing quarterly progress reports · possession by Dec 2026 · Panchshil Hotels Pvt Ltd

Major developers building in Mundhwa

Other RERA-registered projects in Pune

Vertical Oriana Phase III
declared completion Dec 2021 · Vertical Infra
Vertical Oriana Phase IV
declared completion Sep 2023 · Vertical Infra
Vertical Oriana Phase V
possession by Dec 2026 · Vertical Infra
Vertillas
declared completion Mar 2026 · AMI Estates LLP
Vetro Apartments PH I
possession by Mar 2028 · AR Landmark LLP
Vibha
declared completion Jun 2019 · BKP Infraa

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026