Plotted Development Intelligence · Pune

VIVID PARK

P52100029303 · PIMPARI CHICHWAD · promoter Mahadev Narayn Kawade

Certificate SignedDue 31 Dec 2023

Delivery & Registration

MahaRERA registrationP52100029303
Registered on18 May 2021
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Mahadev Narayn Kawade is the promoter of record on 73 projects, of which 11 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at PIMPARI CHICHWAD , CHAROLI , Beed, Beed, 412105. Per the filed land record, the plot is bounded to the north by PROPERTY NUMBER 137-2 137-3, to the south by PROPERTY NUMBER BP CHAROLI 10-2020, to the east by 18 METER DEVELOPMENT ROAD and to the west by PROPERTY NUMBER BP CHAROLI 10-2020. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~159 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)158 km
Kharadi / EON IT Park159 km
Magarpatta / Hadapsar IT162 km
Pune Junction / city centre166 km
Baner–Balewadi belt172 km
Hinjewadi Rajiv Gandhi IT Park174 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Moshi

Swastik Twin Tower
possession by Jul 2026 · Swastik Builders
Asha Paradise
possession by Jul 2026 · G T Buildcon
Dhrupi Towers
possession by Jul 2026 · Not Available
RKL Durvankur Jaswand
possession by Jul 2026 · Lunkad Vishwa Developer
Amora Tower
possession by Aug 2026 · Amarnath Creativity
Prime Space
possession by Aug 2026 · Nath Estate

Major developers building in Moshi

Other RERA-registered projects in Pune

Vizion Bliss
declared completion Jun 2026 · Vizion Construction
Vizion Galaxy A
declared completion Jan 2018 · Vizion Construction
Vizion Galaxy B
declared completion Dec 2017 · Vizion Construction
Vizion Galaxy C
declared completion May 2018 · Vizion Construction
Vizion Galaxy D
possession by Dec 2026 · Vizion Construction
VJ 67 K Inclusive Housing
declared completion Dec 2023 · Vilas Javdekar Greenscape Developers LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026