Bangalore/Project record

K-RERA · the public record

ADARSH TRANQVILLE

Bengaluru East · Varin Infra Projects

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

100%construction reportedQ4 2025 filing
8units not bookedof 81 · Q4 2025 filing
31 Aug 2020declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q4 2025

declared completion

31 Aug 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

14.2registered acres

5.7registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/181210/002211

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 August 2020
Land area57,338 sq m (14.2 acres)
Homes registered81
Tower/wing entries74

In context

Density5.7 homes per acre
Density in context1st percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units81Total inventory registered with K-RERA.
Registered land area57,338 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI0.786Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries74Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)147Separate filed counts; these categories may overlap and are not added together.
Open-parking field14Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date01-06-2018

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
1212-
3212-
5212-
6212-
7212-
8212-
11212-
13212-

Showing first 8 of 74 tower/wing rows.

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 81 official flat/unit rows, matching the 81 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
4BHK63249.1-297.2 sqm0.0 sqm126
3.5BHK10202.4-204.4 sqm0.0 sqm20
1BHK825.1-28.9 sqm0.0 sqm1 (7 with 0)

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
PLOT NO 60825.1-28.9 sqm0.0 sqm1 (7 with 0)
11256.3 sqm0.0 sqm2
1001202.4 sqm0.0 sqm2
1011202.4 sqm0.0 sqm2
1031204.4 sqm0.0 sqm2
1041204.4 sqm0.0 sqm2
1051204.4 sqm0.0 sqm2
1061204.4 sqm0.0 sqm2
111251.8 sqm0.0 sqm2
131251.8 sqm0.0 sqm2
141251.8 sqm0.0 sqm2
151251.8 sqm0.0 sqm2

Showing first 12 of 74 tower/wing groups.

Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1104BHK256.3 sqm0.0 sqm2
3304BHK256.3 sqm0.0 sqm2
5504BHK251.8 sqm0.0 sqm2
6604BHK251.8 sqm0.0 sqm2
7704BHK251.8 sqm0.0 sqm2
8804BHK251.8 sqm0.0 sqm2

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

⚠ 1 litigation case on record

  • Katha challenge — High Court of karnataka (2018)

⚠ 2 of 21 compliance document slots are filed as under process / not yet usable: Brochure of Current Project, Project Photo Uploaded.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Aug 2020, extended (Extension) to 06 Mar 2026 — both dates have passed with no OC on file. The extension on file was granted on 19 Feb 2021 (K-RERA extension no. EX/PRM/KA/RERA/1251/446/PR/210219/002211) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)Not found in catalog
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

2 K-RERA orders on this project (PROJECT EXTENSION) — read the order copies on the K-RERA portal.

K-RERA complaint orders (1 complaint against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Harshil Bazari vs Varin Infra Projects Private LimitedDelay Period InterestAUTHORITY09/07/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (2 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/211013/0008438
13-10-2021
Refund of the advance payment and compensation after cancellation due to builder could not furnish required important documents pertaining to landADARSH WISTERIA PHASE 1 (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/211029/0008505
29-10-2021
REFUND OF ADVANCE AND COMPENSATIONADARSH WISTERIA PHASE 1 (another project by this promoter)DISPOSED AUTHORITY BENCH6

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note Fire NOC is not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows it as "not found in catalog", that is why; ask the builder directly whether it applies here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

8 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
KSPCB- PCB (10 Acres to 125 Acres)Approved16-05-2023Tranqville CFE.pdf
KSPCB- MOEF (Above 50 Acres)Approved28-04-2017SEIAA tranqville.pdf

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectC B Vivek Uthaiah-2000Raheja Chambers, 12-Museum Road
ContractorRAMYA CONSTRUCTIONS-2005RAMAKRISHNANAGAR, NANDINI LAY OUT
Structural engineerDesigntree Service Consultants Pvt Ltd---

Builder track record

RERA filing

Varin Infra has 2 other K-RERA-registered projects in our records (average reported construction progress 98%). 1 is past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹183.06 Cr collected from buyers, ₹243.76 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹243.76 Cr) exceeded buyer collections (₹183.06 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress100% → 100% (+0 pts)
Units sold/booked as registered73/81 (90%)
Buyer collections in available QPRs₹361.19 Cr
Escrow withdrawals in available QPRs₹487.52 Cr (1.35x collections)
  • Across available QPR rows, escrow withdrawals are 1.35x buyer collections. Ask the builder to reconcile this against certified project costs and prior-period balances.
  • In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹241.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Richmond Road (IFSC HDFC0000523, a/c …6474). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Outer Ring Road / Manyata6 km
MG Road / city centre13 km
Kempegowda Int'l Airport14 km
Whitefield IT hub16 km
Bellandur–Marathahalli belt17 km
Electronic City26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Varin Infra.
Varin Infra has 3 projects registered in Bangalore, 2 completed.

Other projects by this builder in Bangalore

Adarsh Pinecourt
Filing overdue · 98% built · 71% sold
Adarsh Wisteria Phase 1
No filings

Other RERA-registered projects in Kothanur

Major developers building in Kothanur

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Adarsh Tranqville?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026