ARYAN GOLDEN ARENA - B

Bengaluru South · ARYAN HOMETEC

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2018declared completionK-RERA registration · read 20 Sep 2026
72registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

0.6registered acres

129.4registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/171118/001382

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2018
Land area2,252 sq m (0.6 acres)
Homes registered72
Tower/wing entries1

In context

Density129.4 homes per acre
Density in context92nd percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units72Total inventory registered with K-RERA.
Registered land area2,252 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.74Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)80Separate filed counts; these categories may overlap and are not added together.
Open-parking field7Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date14-12-2015

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Aryan Golden Arena B97280-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 72 official flat/unit rows, matching the 72 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK54670.0-680.0 sqft285.3-288.1 sqft54
2BHK18424.0-554.0 sqft176.5-231.2 sqft18

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Aryan Golden Arena B72424.0-680.0 sqft176.5-288.1 sqft72
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
B-101Aryan Golden Arena B12BHK424.0 sqft176.5 sqft1
B-102Aryan Golden Arena B13BHK678.0 sqft285.3 sqft1
B-103Aryan Golden Arena B13BHK680.0 sqft288.1 sqft1
B-104Aryan Golden Arena B13BHK670.0 sqft285.3 sqft1
B-105Aryan Golden Arena B13BHK670.0 sqft285.3 sqft1
B-106Aryan Golden Arena B12BHK554.0 sqft231.2 sqft1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 17 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2018, extended (Section 6 Extension) to 31 Dec 2019 — both dates have passed with no OC on file. The extension on file was granted on 22 Jun 2022 (K-RERA extension no. EX/PRM/KA/RERA/1251/310/PR/220622/001382) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (6 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Sudha Menon vs ARYAN HOMETEC PVT LTDProject Completion and flat registration and possession at the earliestAUTHORITY29/12/2025
Giduthuri Vara Lakshmi vs ARYAN HOMETEC PVT LTDProject Stalled - Builder absconding - Appeal for Money RefundAUTHORITY29/12/2025
Venkateswarlu Pasupuleti vs ARYAN HOMETEC PVT LTDPlease give my flat or my money back from the builder. I am depressed for last 8 years.AUTHORITY29/12/2025
S R Saravanan vs ARYAN HOMETEC PVT LTDKindly help to get my flat or refund from builder.AUTHORITY20/09/2022
MRINAL SHANKAR vs ARYAN GOLDEN ARENA BDierct builder to close the outstanding loan amount and refund the PEMI/EMI paid along with initial amount paid at the time of booking.AUTHORITY12/03/2024
kotresh Rakesh Roshan vs ARYAN GOLDEN ARENA - BAmount should be refunded along with the interest or the project should be handed over within the stipulated time with all basic amenities so that the flat owners can start residing there with no issuAUTHORITY03/03/2026

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (62 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190426/0002768
26-04-2019
Booking Amount RefundARYAN GOLDEN ARENA - D (another project by this promoter)DISPOSED AO
CMP/190613/0003277
13-06-2019
Non hand over of flatARYAN GOLDEN ARENA - C (another project by this promoter)DISPOSED AO
CMP/190715/0003529
15-07-2019
Refund of moneyARYAN GOLDEN ARENA - E (another project by this promoter)DISPOSED AO
CMP/191008/0004435
08-10-2019
Non delivery of Flat and not able to meet promoterARYAN GOLDEN ARENA - C (another project by this promoter)DISPOSED AO
CMP/191023/0004072
23-10-2019
PRE EMI iSSUEARYAN GOLDEN ARENA - F (another project by this promoter)DISPOSED AO
CMP/191028/0004569
28-10-2019
Delay in ConstructionARYAN GOLDEN ARENA - F (another project by this promoter)DISPOSED AO
CMP/191121/0004782
21-11-2019
Refund of booking amountARYAN GOLDEN ARENA - G (another project by this promoter)DISPOSED AO
CMP/191121/0004780
21-11-2019
Refund of Booking AmountARYAN GOLDEN ARENA - F (another project by this promoter)DISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Architect, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectRamesha DB - Landmark Architects & Engineers-201422nd Main, JP Nagar 2nd Phase
Structural engineerG. Praveen Kumar - ECO Consultants---

Builder track record

RERA filing

Aryan Hometec has 8 other K-RERA-registered projects in our records. 8 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a higher delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹8.6 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Indian Bank JP Nagar. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Electronic City14 km
Bellandur–Marathahalli belt18 km
Whitefield IT hub18 km
MG Road / city centre27 km
Outer Ring Road / Manyata32 km
Kempegowda Int'l Airport44 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Aryan Hometec. View Aryan Hometec's full track record →
Aryan Hometec has 9 projects registered in Bangalore.
1 complaints on the K-RERA register against Aryan Hometec in Bangalore.

Other projects by this builder in Bangalore

Aryan Golden Arena - C
No filings
Aryan Golden Arena - D
No filings
Aryan Golden Arena - E
No filings
Aryan Golden Arena - F
No filings

Other RERA-registered projects in BEML Cooperative Society Layout

Sobha Manhattan Towers-Town Park Phase 1 W 4 & 5

Major developers building in BEML Cooperative Society Layout

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Aryan Golden Arena - B?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026