68%construction reportedQ1 2026 filing
43units not bookedof 68 · Q1 2026 filing
31 Dec 2026declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

2 BHK
27
3 BHK
41

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

0.9registered acres

73.5registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/309/PR/040524/006853

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2026
Land area3,743 sq m (0.9 acres)
Homes registered68
Tower/wing entries1
Unit mix27 × 2 BHK, 41 × 3 BHK

In context

Density73.5 homes per acre
Density in context48th percentile of 525 Bengaluru North projects (median 75.4)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units68Total inventory registered with K-RERA.
Official carpet area8,261 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area11,076 sqmUseful scale context when comparing density and project cost.
Registered land area3,743 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.23Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)68Separate filed counts; these categories may overlap and are not added together.
Covered-parking field75Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan number228/15-16Use this to match the sanctioned drawing set shown by the builder.
Plan approval date29-11-2016
Project start date01-08-2022

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2 BHK2740%1,984 sqm
3 BHK4160%3,608 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
B V MAPLE5686818.45 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 68 official flat/unit rows, matching the 68 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK4188.0 sqm109.0 sqm41
2 BHK2768.0-88.0 sqm83.0-109.0 sqm27

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
B V MAPLE6868.0-88.0 sqm83.0-109.0 sqm68
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1B V MAPLE03 BHK88.0 sqm109.0 sqm1
2B V MAPLE03 BHK88.0 sqm109.0 sqm1
3B V MAPLE03 BHK88.0 sqm109.0 sqm1
4B V MAPLE03 BHK88.0 sqm109.0 sqm1
5B V MAPLE03 BHK88.0 sqm109.0 sqm1
6B V MAPLE02 BHK68.0 sqm83.0 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

15 of 43 compliance document slots are filed as Not Applicable; the remaining 28 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearanceNot found in catalog
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note environmental clearance and pollution-control clearance (KSPCB) are not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows them as "not found in catalog", that is why; ask the builder directly whether they apply here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

5 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved07-08-2015Water NOC.pdf
KPTCL- BESCOMApproved13-12-2022Bescom Noc.pdf
Fire and SafetyApproved11-09-2015Fire Noc.pdf
Airport Authority of IndiaApproved27-08-2015AAI.pdf
BSNL/Telecommunication DepartmentApproved05-06-2015BSNLNoc.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantM PRASAD & Co.,2019160000Bengaluru Urban, Karnataka - 560004
EngineerSundareshan VBCC/BL-3.6/SE-0087/22-232022Bengaluru Urban, Karnataka - 560021
ArchitectPRUDHVI RCA/2019/1139982019Bengaluru Urban, Karnataka - 560048
ContractorB V MAPEL-2022Bengaluru Urban, Karnataka - 560091

Builder track record

RERA filing

Promoters has 7 other K-RERA-registered projects in our records. 5 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹0.00 Cr collected from buyers, ₹7.58 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹7.58 Cr) exceeded buyer collections (₹0.00 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress33% → 68% (+35 pts)
Units sold/booked as registered25/68 (37%)
Escrow withdrawals in available QPRs₹12.42 Cr
  • Construction progress moved from 33% to 68% across the filed QPR window.
  • In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹41.8 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Karnataka Bank Ltd.. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Electronic City13 km
MG Road / city centre14 km
Bellandur–Marathahalli belt17 km
Outer Ring Road / Manyata21 km
Whitefield IT hub25 km
Kempegowda Int'l Airport41 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Promoters.
Promoters has 8 projects registered in Bangalore.
3 complaints on the K-RERA register against Promoters in Bangalore.

Other projects by this builder in Bangalore

Other RERA-registered projects in Talaghattapura

Major developers building in Talaghattapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.