Bangalore/Project record

K-RERA · the public record

Provident Park Square Phase - 1

Bengaluru South · Puravankara

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2021declared completionK-RERA registration · read 20 Sep 2026
662registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

7.4registered acres

89.9registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/180217/002476

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2021
Land area29,791 sq m (7.4 acres)
Homes registered662
Tower/wing entries6

In context

Density89.9 homes per acre
Density in context70th percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units662Total inventory registered with K-RERA.
Registered land area29,791 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.249Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries6Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)662Separate filed counts; these categories may overlap and are not added together.
Open-parking field195Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date31-12-2017

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
B1-1C14119119-
B1-1D14119119-
B2-2D13104104-
B2-2E13104104-
B3-3E13104104-
B4-4A14112112-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 662 official flat/unit rows, matching the 662 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
1BHK23833.4-44.4 sqm0.0 sqm0 (238 with 0)
2BHK21254.9-56.9 sqm0.0 sqm0 (212 with 0)
3BHK21272.5-83.8 sqm0.0 sqm0 (212 with 0)

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
B1-1C11933.4-44.4 sqm0.0 sqm0 (119 with 0)
B1-1D11933.4-44.4 sqm0.0 sqm0 (119 with 0)
B4-4A11254.9-72.5 sqm0.0 sqm0 (112 with 0)
B2-2D10454.9-83.8 sqm0.0 sqm0 (104 with 0)
B2-2E10454.9-83.8 sqm0.0 sqm0 (104 with 0)
B3-3E10454.9-72.5 sqm0.0 sqm0 (104 with 0)
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
2B1-1C01BHK44.4 sqm0.0 sqm0
3B1-1C01BHK44.4 sqm0.0 sqm0
4B1-1C01BHK33.8 sqm0.0 sqm0
5B1-1C01BHK33.8 sqm0.0 sqm0
6B1-1C01BHK44.4 sqm0.0 sqm0
7B1-1C01BHK44.4 sqm0.0 sqm0

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

3 of 24 compliance document slots are filed as Not Applicable; the remaining 21 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2021, extended (Section 6 Extension) to 30 Sep 2023 — both dates have passed with no OC on file. The extension on file was granted on 21 Dec 2022 (K-RERA extension no. EX/PRM/KA/RERA/1251/310/PR/221221/002476) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (BESCOM)
Water & sewage (BWSSB/KWSSB)✓ On file (BWSSB)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (11 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
NITIN R SHROFF vs Puravankara LimitedWOULD LIKE TO EXIT THE PROJECT AND WOULS REQUEST FOR A FULL REFUND OF INSTALLMENTS AND GST PAID UPTO DATE WITH INTEREST UPTO DATE AS BUILDER HAS BREACHED THE AGREEMENTAUTHORITY25/01/2023
GOPAL B N vs PURAVANKARA LIMITEDwe need extension to pay the pending amount or refund from the builderAUTHORITY24/01/2023
Ravi Kumar P vs Purvankara LimitedPlease help us to get our refund amount which we paid to builder as they are not responding after cancellation of the sale agreement and we are keep following up and the builder is not respondingAUTHORITY22/06/2023
Rajan & Sahana vs Puravankara LimitedExpecting RERA authorities to help us and get the property registered as soon as possible without paying the extra amountAUTHORITY20/06/2024
Rick Mukherjee vs Puruvankara Limited & Keppel Puravankara Development Private LimitedTo instruct the builder to compensate for Home Loan and interest paid for the tenure of the delayAUTHORITY19/03/2024
Sahana Somashekara vs Puravankara LimitedI need my advance booking amount of Rs 2,00,000/- along with interestAUTHORITY12/10/2022
Vasanth Kumar T R vs PURAVANKARA LIMITEDPlease help me to get the booking fee refund as they are denying to give me the refund after the booking cancellation done.AUTHORITY11/07/2023
PRITHWISH CHATTERJEE & ANOTHER vs PURVANKARA LIMITEDImmediate allotment of parking space as per Sale Deed and payment of interest on delay periodAUTHORITY07/10/2024
arun vs Puravankara LimitedDirect promoter to obtain ekhata and register flat or else refund 6,86,000 with RERA interest u/s 18 for delay peroid.AUTHORITY02/12/2025
Mohan Madaiah vs provident park square phase 11 year extension compensation.AUTHORITY01/08/2025
Pratap R vs PURUVANKARA LIMITEDRefund of booking amountAUTHORITY01/03/2023

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (53 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190321/0002481
21-03-2019
Refund of 2lac rupees token amountProvident Park Square Phase - 1DISPOSED AO
CMP/190416/0002487
16-04-2019
Delay of flat delivery and Compensation as per Rera actPurva Westend Phase 1 (another project by this promoter)DISPOSED AO
CMP/190501/0002703
01-05-2019
Misguided ,Forced to pay 10% and with out SBI approval of Tower -not given Requested FlatProvident Park Square Phase - 1DISPOSED AO
CMP/190511/0002977
11-05-2019
NON REGISTRATION AND POSSESSION OF FLAT DELIVERY DATE EXPIREDPurva Sunflower (another project by this promoter)DISPOSED AO
CMP/190525/0003132
25-05-2019
Appeal for invoking section 18 of RERA Act for continuous delay in handover of apartmentPurva Westend Phase 1 (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/190611/0003274
11-06-2019
Builder is not responding to: cancellation of agreement by buyer due to delay in completionPurva Sunflower (another project by this promoter)DISPOSED AO
CMP/190618/0003322
18-06-2019
Booking amount refund 2 lakhsProvident Park Square 4 (another project by this promoter)DISPOSED AO
CMP/190714/0003570
14-07-2019
Complaint under Sec 18, Sec 31 & Sec 71 of the Real Estate (Regulation and Development) Act 2016, and under Rule 17, 29 & 30 of the Karnataka Real Estate (Regulation and Development) Rules 2017.Purva Palmbeach (another project by this promoter)DISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 1 project professional/vendor row across Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ContractorStarworth Infrastructure and Constructions Limited-200939 Ulsoor Road, Yellappa Chetty Layout

Builder track record

RERA filing

Puravankara has 30 other K-RERA-registered projects in our records (average reported construction progress 79%). 13 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹31.8 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Standard Chartered Bank Koramangala (IFSC SCBL0036073, a/c …4380). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Electronic City13 km
MG Road / city centre14 km
Bellandur–Marathahalli belt18 km
Outer Ring Road / Manyata22 km
Whitefield IT hub26 km
Kempegowda Int'l Airport41 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Puravankara. View Puravankara's full track record →
Puravankara has 31 projects registered in Bangalore, 6 completed, 1 past RERA deadline.
2 complaints on the K-RERA register against Puravankara in Bangalore.

Buyer reviews · MouthShut

★★☆☆☆ 1.52/5

663 reviews for Puravankara in Bangalore
Read 663 reviews on MouthShut →

Other projects by this builder in Bangalore

Provident Park Square 5
Past deadline · 91% built · 99% sold
Provident Deansgate
Filing overdue · 76% built · 88% sold
Provident Deansgate Phase 2
Filing overdue · 24% built · 60% sold
Purva Blubelle
Filing overdue · 35% built · 89% sold
Purva Oakshire
Filing overdue · 100% built
Purva Orient Grand
Filing overdue · 51% built · 11% sold

Other RERA-registered projects in Talaghattapura

Major developers building in Talaghattapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Provident Park Square Phase - 1?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026