Bangalore/Project record

K-RERA · the public record

BHUVANA BOULEVARD PHASE 2

Hosakote · VSPR DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

10%construction reportedQ1 2026 filing
24units not bookedof 28 · Q1 2026 filing
31 Dec 2030declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Dec 2030

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

4 BHK
28

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

1.4registered acres

19.6registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1250/304/PR/170425/007676

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2030
Land area5,768 sq m (1.4 acres)
Homes registered28
Tower/wing entries1
Unit mix28 × 4 BHK

In context

Density19.6 homes per acre
Density in context13th percentile of 112 Hosakote projects (median 79.1)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units28Total inventory registered with K-RERA.
Official carpet area5,348 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area1,317 sqmUseful scale context when comparing density and project cost.
Registered land area5,768 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.06Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)28Separate filed counts; these categories may overlap and are not added together.
Covered-parking field28Separate filed counts; these categories may overlap and are not added together.
Open-parking field3Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberHPA/CC/509/2023-24/2627Use this to match the sanctioned drawing set shown by the builder.
Plan approval date09-01-2025
Project start date01-03-2025

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
4 BHK28100%5,349 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
BHUVANA BOULEVARD PHASE 22282810 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 28 official flat/unit rows, matching the 28 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
4 BHK28178.0-267.0 sqm187.0-250.0 sqm28

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
BHUVANA BOULEVARD PHASE 228178.0-267.0 sqm187.0-250.0 sqm28
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
B1BHUVANA BOULEVARD PHASE 204 BHK211.0 sqm244.0 sqm1
B2BHUVANA BOULEVARD PHASE 204 BHK183.0 sqm199.0 sqm1
B3BHUVANA BOULEVARD PHASE 204 BHK183.0 sqm199.0 sqm1
B4BHUVANA BOULEVARD PHASE 204 BHK183.0 sqm199.0 sqm1
B5BHUVANA BOULEVARD PHASE 204 BHK189.0 sqm187.0 sqm1
B6BHUVANA BOULEVARD PHASE 204 BHK228.0 sqm250.0 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

11 of 31 compliance document slots are filed as Not Applicable; the remaining 20 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note Fire NOC and environmental clearance are not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows them as "not found in catalog", that is why; ask the builder directly whether they apply here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

7 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved28-05-2024Water 28-5-24.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved27-12-2023KSPCB 27-12-23.pdf
KPTCL- BESCOMApproved04-02-2024BESCOM 4-2-24.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantJayatheertha K B2020072022Bengaluru Urban, Karnataka - 560003
EngineerMADAMANCHI SURENDRA NADHBCCUBL-3.6/SE 0333/21-222021Guntur, Andhra Pradesh - 522647
ArchitectA S YatirajCA/2007/398932020Bengaluru Urban, Karnataka - 560079
ContractorVSPR DEVELOPERS-2023Bengaluru Urban, Karnataka - 560094

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹0.87 Cr collected from buyers, ₹0.85 Cr withdrawn from the project's escrow account.

Construction progress9% → 10% (+1 pts)
Units sold/booked as registered4/28 (14%)
Buyer collections in available QPRs₹2.76 Cr
Escrow withdrawals in available QPRs₹1.86 Cr (0.67x collections)
  • Construction progress moved from 9% to 10% across the filed QPR window.
  • The builder has drawn 0.67x of buyer collections from escrow (about 67% of the ₹3 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹86.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: IDFC FIRST BANK HSR LAYOUT IFSC Code : IDFB0080172 Pin Code : 560102. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Whitefield IT hub5 km
Bellandur–Marathahalli belt10 km
Electronic City16 km
MG Road / city centre19 km
Outer Ring Road / Manyata21 km
Kempegowda Int'l Airport30 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Vspr Developers.
Vspr Developers has 2 projects registered in Bangalore.

Other projects by this builder in Bangalore

Bhuvana Boulevard Phase 1
On track · 11% built · 4% sold

Other RERA-registered projects in Balagere

Major developers building in Balagere

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Bhuvana Boulevard Phase 2?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026