Brigade Oasis - Phase 1
Devanahalli · Brigade Enterprises
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Promoter-reported construction
K-RERA quarterly filings · Q3 2025 to Q1 2026
declared completion
30 Jun 2025
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
K-RERA registration · read 20 Sep 2026
Inventory & scale
What this registration contains.
Filed categories, unchanged · K-RERA registration · read 20 Sep 2026
The whole registration
The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
K-RERA · PRM/KA/RERA/1250/303/PR/041122/005401
This project, on the record
The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.
On the register
Values as crawled from the official K-RERA record; context percentiles name their comparison population.
Official Registry Facts
Official project scale
RERA filingRegistration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.
| Disclosure | Official value | Why it matters |
|---|---|---|
| Approved plan number | STRRPA/TP/LAO/19/2022-23 | Use this to match the sanctioned drawing set shown by the builder. |
| Plan approval date | 08-08-2022 | |
| Project start date | 02-11-2022 |
Official inventory & towers
RERA filingK-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.
Registered inventory mix
| Type | Units | Share | Official carpet area |
|---|---|---|---|
| 12.19 X 18.29 M (222.96 SQM) | 51 | 100% | 0 sqm |
Legal, Approvals & Project Team
Litigation & compliance
RERA filing⚠ Developer declared litigation on this land/property.
27 of 44 compliance document slots are filed as Not Applicable; the remaining 17 slots have usable uploaded filings.
No completion certificate (OC) on file yet — project has not been declared complete.
⚠ Registration validity has lapsed: originally due 30 Jun 2025, extended (Section 6 Extension) to 30 Jun 2026 — both dates have passed with no OC on file. The extension on file was granted on 27 Jun 2025 (K-RERA extension no. EX/PRM/KA/RERA/1250/303/PR/250627/005401) — it has been used, its deadline has also passed, and no further extension is recorded.
Named utility/regulatory approvals
"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.
Complaints on this project's K-RERA page (21 complaints listed against this promoter)
| Complaint | Subject (as filed) | Project | Status |
|---|---|---|---|
| CMP/190802/0003774 02-08-2019 | Project delay compensation & Veracity of the agreement & Brochure while booking | Brigade Panorama (another project by this promoter) | DISPOSED AO |
| CMP/190915/0004196 15-09-2019 | Waiting period more than 1.5 years, amenities built on kharab land, Club house not as per agreement | Brigade Panorama (another project by this promoter) | DISPOSED AO |
| CMP/190920/0004245 20-09-2019 | Delay in paying the Delay Compensation | Brigade Panorama (another project by this promoter) | DISPOSED AO |
| CMP/200211/0005414 11-02-2020 | Brigade group not given the compensation as per RERA and changes in the layout plan | Brigade Panorama (another project by this promoter) | DISPOSED AUTHORITY BENCH6 |
| CMP/200513/0005880 13-05-2020 | Refund of amount due to delay in registration/handover | Brigade Panorama (another project by this promoter) | DISPOSED AUTHORITY BENCH6 |
| CMP/201130/0007159 30-11-2020 | Brigade has backed out of delay compensation payment after earlier assuring to pay the same | Brigade Panorama (another project by this promoter) | DISPOSED AUTHORITY BENCH6 |
| CMP/210212/0007498 12-02-2021 | Recovery of delay compensation, rental loss & Property tax amount with Interest for 6 years of delay caused by builder to deliver possession of flat | Plumeria Lifestyle at Brigade Meadows (another project by this promoter) | DISPOSED AUTHORITY BENCH4 |
| CMP/210512/0007948 12-05-2021 | BUILDER NOT ALLOWING INSPECTION OF OUR APARTMENT | Brigade Buena Vista-Phase 2 (another project by this promoter) | DISPOSED AUTHORITY BENCH4 |
Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.
Statutory approval status
RERA filingClean approvals profile: every applicable statutory NOC is on file — including pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note Fire NOC and environmental clearance are not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows them as "not found in catalog", that is why; ask the builder directly whether they apply here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.
10 further authority slots are marked not applicable by the regulator.
| Authority / NOC | Status | Date | File |
|---|---|---|---|
| KSPCB- PCB (10 Acres to 125 Acres) | Approved | 07-11-2022 | Consent for Establishment 1 (2).pdf |
Project team & certifications
RERA filingK-RERA names 2 project professional/vendor rows across Chartered accountant, Engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.
| Role | Name | Registration / licence | Since | Locality |
|---|---|---|---|---|
| Chartered accountant | R. Srinivasan | 28986 | 2000 | Bengaluru Urban, Karnataka - 560003 |
| Engineer | Vijay Kumar | BCC/BL-3.6/E-3949/2014-15 | 2004 | Bengaluru Urban, Karnataka - 560027 |
Builder track record
RERA filingBrigade has 60 other K-RERA-registered projects in our records — grouped across the several project-specific entities this developer registers under (e.g. this project is filed as “Brigade Enterprises”) (average reported construction progress 68%). 31 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.
Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.
Financials & Construction Progress
Financial disclosures
RERA filingLatest quarterly filing (2026-Q1): ₹8.34 Cr collected from buyers, ₹36.28 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹36.28 Cr) exceeded buyer collections (₹8.34 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.
| Construction progress | 83% → 100% (+17 pts) |
| Buyer collections in available QPRs | ₹9.11 Cr |
| Escrow withdrawals in available QPRs | ₹37.05 Cr (4.07x collections) |
- Construction progress moved from 83% to 100% across the filed QPR window.
- Across available QPR rows, escrow withdrawals are 4.07x buyer collections. Ask the builder to reconcile this against certified project costs and prior-period balances.
- In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.
QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.
The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.
RERA 70% project account is on file: KOTAK MAHINDRA BANK Lavelle Road, Bangalore IFSC Code : KKBK0000422 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.
Location & Connectivity
The nearest major job hub is ~26 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Kempegowda Int'l Airport | 9 km |
| Outer Ring Road / Manyata | 26 km |
| MG Road / city centre | 33 km |
| Whitefield IT hub | 34 km |
| Bellandur–Marathahalli belt | 37 km |
| Electronic City | 47 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.