Prestige Sanctuary

Devanahalli · VILLAGE DE NANDI

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

100%construction reportedQ1 2026 filing
0units not bookedof 85 · Q1 2026 filing
30 Nov 2025declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

30 Nov 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Villa Type C
24
Villa Type B
19
Villa Type A
42

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

22.9registered acres

3.7registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1250/303/PR/101122/005448

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 November 2025
Land area92,874 sq m (22.9 acres)
Homes registered85
Tower/wing entries1
Unit mix24 × Villa Type C, 19 × Villa Type B, 42 × Villa Type A

In context

Density3.7 homes per acre
Density in context0th percentile of 72 Devanahalli projects (median 68.1)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units85Total inventory registered with K-RERA.
Official carpet area28,441 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area38,506 sqmUseful scale context when comparing density and project cost.
Registered land area92,874 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI0.42Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)85Separate filed counts; these categories may overlap and are not added together.
Covered-parking field115Separate filed counts; these categories may overlap and are not added together.
Open-parking field40Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBIAAPA/TP/LOA/DP/106/2021-2022Use this to match the sanctioned drawing set shown by the builder.
Plan approval date13-05-2022
Project start date01-12-2022

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Villa Type C2428%10,590 sqm
Villa Type B1922%6,550 sqm
Villa Type A4249%11,301 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Prestige Sanctuary1858515 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 85 official flat/unit rows, matching the 85 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
4 BHK85269.1-441.3 sqm283.0-788.6 sqm85

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Prestige Sanctuary85269.1-441.3 sqm283.0-788.6 sqm85
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1Prestige Sanctuary04 BHK269.1 sqm390.3 sqm1
B2+1Prestige Sanctuary04 BHK269.1 sqm390.3 sqm1
B3+1Prestige Sanctuary04 BHK269.1 sqm390.3 sqm1
B4+1Prestige Sanctuary04 BHK269.1 sqm390.3 sqm1
B5+1Prestige Sanctuary04 BHK269.1 sqm390.3 sqm1
B6+1Prestige Sanctuary04 BHK269.1 sqm390.3 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

11 of 31 compliance document slots are filed as Not Applicable; the remaining 20 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Nov 2025, extended (Section 6 Extension) to 31 May 2026 — both dates have passed with no OC on file. The extension on file was granted on 17 Dec 2025 (K-RERA extension no. EX/PRM/KA/RERA/1250/303/PR/251217/005448) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)Not found in catalog
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note Fire NOC is not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows it as "not found in catalog", that is why; ask the builder directly whether it applies here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

5 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved08-11-2022WATER NOC.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved19-09-2022KSPCB.pdf
KSPCB- MOEF (Above 50 Acres)Approved22-08-2022MOEF.pdf
KPTCL- BESCOMApproved26-09-2022BESCOM NOC.pdf
Airport Authority of IndiaApproved07-07-2023AIRPORT NOC.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantM Padmanabha Bhat0253051986Bengaluru Urban, Karnataka - 560093
EngineerMr. Naushad Ali HBCC/BL-3.6/SE-0322/2019-201993Bengaluru Urban, Karnataka - 560027
ArchitectMr. Tilak ThomasCA/99/252821992Bengaluru Urban, Karnataka - 560001
ContractorK2K Infrastructure (I) Pvt Ltd-2007Bengaluru Urban, Karnataka - 560050

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹5.02 Cr collected from buyers, ₹14.52 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹14.52 Cr) exceeded buyer collections (₹5.02 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress97% → 100% (+3 pts)
Units sold/booked as registered85/85 (100%)
Buyer collections in available QPRs₹25.52 Cr
Escrow withdrawals in available QPRs₹46.52 Cr (1.82x collections)
  • 100% of registered units are shown as sold/booked, but no completion certificate is on file yet.
  • Construction progress moved from 97% to 100% across the filed QPR window.
  • The filed unit sales count did not move across the available QPR window because the project was already effectively sold out.
  • Across available QPR rows, escrow withdrawals are 1.82x buyer collections. Ask the builder to reconcile this against certified project costs and prior-period balances.
  • In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹183.0 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: KOTAK MAHINDRA BANK Lavelle Road IFSC Code : KKBK0000422 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~31 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kempegowda Int'l Airport13 km
Outer Ring Road / Manyata31 km
Whitefield IT hub39 km
MG Road / city centre39 km
Bellandur–Marathahalli belt42 km
Electronic City52 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Village De.

Other RERA-registered projects in Abbachikkanahalli

Assetz Promise Of Spring Phase-1

Major developers building in Abbachikkanahalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.