D C CAPITOL PHASE – II

Bengaluru East · D.C.HI-RISE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

79%construction reportedQ1 2026 filing
71units not bookedof 164 · Q1 2026 filing
31 Dec 2028declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

2 BHK
68
3 BHK
96

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

1.8registered acres

89.9registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/041024/007120

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2028
Land area7,379 sq m (1.8 acres)
Homes registered164
Tower/wing entries1
Unit mix68 × 2 BHK, 96 × 3 BHK

In context

Density89.9 homes per acre
Density in context74th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units164Total inventory registered with K-RERA.
Official carpet area13,684 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area22,483 sqmUseful scale context when comparing density and project cost.
Registered land area7,379 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.19Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)187Separate filed counts; these categories may overlap and are not added together.
Covered-parking field187Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBBMP/Ad.Com./MDP/0991/23-24Use this to match the sanctioned drawing set shown by the builder.
Plan approval date03-02-2024
Project start date01-07-2024

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2 BHK6841%4,856 sqm
3 BHK9659%8,827 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
B316418714.4 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 164 official flat/unit rows, matching the 164 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK9682.2-108.3 sqm44.0-56.7 sqm96
2 BHK6867.2-77.6 sqm35.9-42.6 sqm68

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
B16467.2-108.3 sqm35.9-56.7 sqm164
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
G01B03 BHK99.2 sqm50.3 sqm1
G02B03 BHK85.5 sqm44.0 sqm1
G03B03 BHK92.6 sqm46.4 sqm1
G04B03 BHK93.9 sqm49.0 sqm1
G05B03 BHK93.9 sqm52.8 sqm1
G06B02 BHK72.7 sqm37.1 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

4 of 28 compliance document slots are filed as Not Applicable; the remaining 24 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Complaints on this project's K-RERA page (1 complaint listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/220107/0008772
07-01-2022
Refusing to sale flat (flat no 122) after agreement and giving it to someone elseDC CAPITOL (another project by this promoter)DISPOSED AUTHORITY BENCH5

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

10 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantCA RAGHU NADHA MANDADI G2078462003Bengaluru Urban, Karnataka - 560004
EngineerARUN KUMAR S RBCC/BL-3.6/SE-0160/2023-242023Bengaluru Urban, Karnataka - 560070
ArchitectBhanumathy GCA/94/167501996Bengaluru Urban, Karnataka - 560070
ContractorD.C.HI-RISE LLP-2022Bengaluru Urban, Karnataka - 560037

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹11.99 Cr collected from buyers, ₹8.10 Cr withdrawn from the project's escrow account.

Construction progress74% → 79% (+5 pts)
Units sold/booked as registered93/164 (57%)
Buyer collections in available QPRs₹47.04 Cr
Escrow withdrawals in available QPRs₹32.85 Cr (0.70x collections)
  • Construction progress moved from 74% to 79% across the filed QPR window.
  • The builder has drawn 0.70x of buyer collections from escrow (about 70% of the ₹47 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹60.3 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Axis Bank PANATHUR BANGALORE IFSC Code : UTIB0002928 Pin Code : 560103. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bellandur–Marathahalli belt2 km
Whitefield IT hub6 km
Electronic City11 km
MG Road / city centre11 km
Outer Ring Road / Manyata15 km
Kempegowda Int'l Airport29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Hi-Rise.

Other RERA-registered projects in Balagere

Major developers building in Balagere

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.