RERA Property Intelligence Report · Preview

FRONTIER HEIGHTS

FRONTIER SHELTERS · Bengaluru East · K-RERA PRM/KA/RERA/1251/446/PR/171214/001250

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

269
Registered units
₹110.0 Cr
Est. construction cost
Units profiled
43
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units269Total inventory registered with K-RERA.
Official carpet area24,136 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area10,163 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.89Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered towers/wings6Official tower/wing count in the K-RERA detail page.
Parking disclosed320 total (0 open) — 1.19 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Project start date01-03-2017

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
APARTMENT266100%24,136 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
tower - 1154544-
tower - 2154565-
tower - 3156061-
tower - 4156058-
tower - 5155837-
club house4155-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 268 official flat/unit rows vs 269 registered units disclosed above; ask why the row count differs. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK19576.3-80.0 sqft35.0-37.0 sqft195
3BHK59112.7-132.8 sqft51.0-59.0 sqft59
4BHK11130.0-132.8 sqft58.0-59.0 sqft11
COMMERCIAL2256.9-509.8 sqft114.1-226.4 sqft6
NA10.0 sqft0.0 sqft55

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
tower - 36076.3-79.4 sqft35.0 sqft60
tower - 46076.4-76.4 sqft35.0 sqft60
tower - 557113.4-509.8 sqft51.0-226.4 sqft61
tower - 14578.3-112.7 sqft36.0-54.0 sqft45
tower - 24576.7-80.0 sqft35.0-37.0 sqft45
club house10.0 sqft0.0 sqft55
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1011tower - 112BHK78.3 sqft36.0 sqft1
1012tower - 112BHK79.7 sqft36.0 sqft1
1013tower - 113BHK112.7 sqft54.0 sqft1
1021tower - 122BHK78.3 sqft36.0 sqft1
1022tower - 122BHK79.7 sqft36.0 sqft1
1023tower - 123BHK112.7 sqft51.0 sqft1

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~91 sqft — compact homes (1–2BHK / studio territory), not compact stock. This is a large, multi-tower township — 269 homes across 6 towers. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 320 parking spaces for 269 homes (~1.2 per home) — about one space per home — adequate but tight if you have two cars.
Your land share (UDS)Undivided land share averages ~41 sqft per home; across all 269 homes that is ~10% of the plot — on the lower side — the undivided shares sum to noticeably less than the plot, worth asking the builder why before relying on it. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 37 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Nov 2019, extended (Section 6 Extension) to 30 Nov 2020 — both dates have passed with no OC on file. The extension on file was granted on 25 Jan 2023 (K-RERA extension no. EX/PRM/KA/RERA/1251/446/PR/230125/001250) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (64 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
SUMIT AHUJA AND ANOTHER vs FRONTIER SHELTERS PVT. LIMITEDREQUEST RERA TO ATLEAST HELP ME IN GETTING THE POSSESION OF MY FLAT IN LIVABLE CONDITION AND ALSO THE COMPENSATION FOR 1 YEAR DELAYED ALREADY PROJECT AS PER AGREEMENT.AUTHORITY23/01/2025
VIKRAM BHATTA & ANOTHER vs FRONTIER SHELTERS PVT. LIMITEDDelay Compensation as per RERAAUTHORITY23/01/2025
SURAJ JANARDAN GHARAT vs FRONTIER SHELTERS PVT. LTD .Please request builder to pay me compensation same as the rent I need to pay due to delayed possesionAUTHORITY21/04/2023
SIDDHARTH KUMAR SRIVASTAVA &JYOTI SRIVASTAVA vs FRONTIER SHELTERS PVT. LTD .Compensation against the delay in Flat Handover. ***I REPEAT I DO NOT WANT CANCELLATION or REFUND. ***AUTHORITY21/04/2023
RAVI RAJ vs FRONTIER SHELTERS PVT. LTD .Compensation for delay in posession as per rera rules, compensation for rent being paid due to deplay in possesion, speed up the contructionAUTHORITY21/04/2023
RIMSY SAINI &ROHIT SENGAR vs FRONTIER SHELTERS PVT. LTD .To provide compensation for delayed project along with rental expense OTHERWISE honor the buyback from respondent along with interest in earliest time possible as per GOI norms.AUTHORITY21/04/2023
ADITHYA BIKRAM MISHRA &DIBYA JYOTI MISHRA vs FRONTIER SHELTERS PVT. LTD .(i) Direct the respondents to pay delay interest as per Section 16 of the provision of the Karnataka Real Estate Act. legal cost and compensation of Rs. 1500000/-AUTHORITY21/04/2023
MOHIT GUPTA &SADHVI GUPTA vs FRONTIER SHELTERS PVT. LTD .DELAY INTEREST AND COMPENSATIONAUTHORITY21/04/2023
HIMANGSHU LAHKAR vs FRONTIER SHELTERS PVT LTDrefund of Rs. 43,89,123 (Rupees Forty-Three Lakh Eighty-Nine Thousand One Hundred Twenty-Three Only) lakh Ninety-Eight thousand Nine hundred forty-three Only) (i) Paid at the time of booking is Rs. 5,AUTHORITY20/01/2026
ANUSHILA BRAHMA vs FRONTIER SHELTERS PVT. LTDNEED RERA TO TAKE ACTION AGAINST THE BUILDER AND GET POSSESSION DONE AT THE EARLIEST AND ALSO MAKE THEM PAY THE COMPENSATION FOR THE DELAYAUTHORITY18/04/2023
SOMNATH BANERJEE & TAMASA BHATTACHARYA vs FRONTIER SHELTERS PVT LTD.Expecting the refund of the amount along with interest, as per legal notice amount claimed with interest is Rs.6,71,835AUTHORITY16/12/2024
Saurav Khandelwal vs FRONTIER SHELTERS PVT LTDReturn of Booking amout with interestAUTHORITY15/09/2023
ASHISH KUMAR PANDEY vs FRONTIER SHELTERS PVT. LTD.SEEKING THE DIRECTION TO THE RESPONDENT TO HANDOVER THE POSSESSION OF THE FLAT NO. 5073 FORTHWITH. (B) DIRECT THE RESPONDENTS TO PAY COMPENSATION @ 10 % P.A. ON THE TOTAL AMT PAID TILL DATE.AUTHORITY15/09/2023
Rakesh Kumar Padhiary vs FRONTIER SHELTERS PVT LTDCompensation as per Rera guidelines and possession at the earliestAUTHORITY15/09/2023
Sandeep Kumar Pradhan vs FRONTIER SHELTERS PVT LTDCOMPENSATION AS PER RERA GUIDELINES AND POSSESSION AS SOON AS POSSIBLEAUTHORITY15/09/2023
Rakesh Kumar Padhiary vs FRONTIER SHELTERS PVT LTDCOMPLETION OF PROJECT AT THE EARLIEST AND PROVIDE COMPENSATION FOR THE DELAYAUTHORITY15/09/2023
Sravankumar Allu vs FRONTIER SHELTERS PVT LTDplease make the builder finish the project and let the builder pay compensation(20000) for my rentAUTHORITY15/09/2023
Anita Roy vs FRONTIER SHELTERS PVT LTDWe request for legal pressure on the builder/developer to speed up the project/ construction process and assist us in getting our flat along with amenities as promised by the builder.AUTHORITY15/09/2023
Nishant Kumar vs FRONTIER SHELTERS PVT LTDPressurize Builder to complete the project else make him pay back our hard earned moneyAUTHORITY15/09/2023
VARUN KUMAR SINGH vs FRONTIER SHELTERS PVT LTDwe request RERA to instruct Builder to handover my flat as soon as possible by giving some time frame, reimbursement of my EMI & Rent to me which i am paying due to delay. please ban this promotor.AUTHORITY15/09/2023
Ananta Das vs FRONTIER SHELTERS PVT LTDComplainant prays that this Hon'ble Authority may be pleased to direct the respondent developer to complete the project and hand over the flat as agreed by them with interest on delay periodAUTHORITY15/06/2026
VIVIEK TRIPATHI vs FRONTIER SHELTERS PVT.LTDExpedite delivery and compensation for the delay.AUTHORITY14/09/2023
PAYAL BHARGAVA vs FRONTIER SHELTERS PVT. LTD.Compensation for Delay in PossessionAUTHORITY14/09/2023
THIRUMALAI SELVAM vs FRONTIER SHELTERS PVT. LTD.Compensation for delay in PossessionAUTHORITY14/09/2023
JIVESH RANJAN SARKAR vs FRONTIER SHELTERS PVT. LTD.REQUEST RERA TO ATLEAST HELP ME IN GETTING THE POSSESION OF MY FLAT IN LIVABLE CONDITION AND ALSO THE COMPENSATION FROM MAY 2020 FOR DELAYED PROJECT AS PER AGREEMENT AND UPDATE SOLD INVENTORY.AUTHORITY09/10/2023
Sonam Kumar vs FRONTIER SHELTERS PVT LTDRefund of my booking amount of Rs.6,21,000.00 along with the interestAUTHORITY08/06/2026
Sapna Chitlangiya vs FRONTIER SHELTERS PVT LTD(i) Direct the respondents to pay statutory delay interest as per Section 16 of the provision of the Karnataka Real Estate (Regulation and Development) Rules, 2017 r/w provisions of REAL ESTATE (REGULAUTHORITY08/06/2026
Govinda Raj vs FRONTIER SHELTERS PVT LTDThe project should be completed as soon as possible. I need interest for the delay from July 2022 which committed date according to agreement.AUTHORITY08/06/2026
KUNDA SEKAR vs FRONTIER SHELTERS PVT LTDDELIVERY OF POSSESSION AND REGISTRARTION OF FLAT NO. 3052 AS PER RERA GUIDELINESAUTHORITY08/06/2026
Ms Chigarapalli Shruthi Reddy vs FRONTIER SHELTERS PVT LTDDirect the Frontier Shelters Pvt Ltd to refund the amount with interest at SBI MCLR plus 2 percent from 01 April 2020 until refund of amountAUTHORITY08/06/2026
VIKASH SINGH vs FRONTIER SHELTERS PVT LTDI would like compensation for delay as per RERA rulesAUTHORITY07/09/2023
SUSANTA KUMAR vs NOT AN OFFICIAL COPYCompensation from builder as they agreed to me earlier and speed up the construction paceAUTHORITY07/09/2023
ANUPAM MAJUMDR vs NOT AN OFFICIAL COPYCompensation for delay in flat handoverAUTHORITY07/09/2023
VINAY BANSAL vs FRONTIER SHELTERS PVT LTDDelay Compensation as per RERA rulesAUTHORITY07/09/2023
SAHIL RAJARAM SHENVI KHANDEPARKER vs FRONTIER SHELTERS PVT.LTD.Compensation for delay and possession with occupancy certificateAUTHORITY07/09/2023
PRITEE KOTIAN vs FRONTIER SHELTERS PVT LTDRequest you to help provide compensation for the rent I am paying and plus the EMI I need to pay to the bank due to this delay.AUTHORITY07/09/2023
BALAKUMAR S vs FRONTIER SHELTERS PVT LTDNeed compensation for the delay in handing over the flat to overcome the financial and mental stress. Flat handover at the earliest. Specifications to be aligned as per the agreementAUTHORITY07/09/2023
PRABHAT KUMAR vs FRONTIER SHELTERS PVT LTDrefund of entire money paid along with stautory interest at the highest MCLR rate Plus 2% as per rule 16, Rs. 15,00,000/- Compensation, Rs. 150000 as legal costAUTHORITY07/09/2023
MANIKANTA T G vs FRONTIER SHELTERS PVT LTDExpectation of confirmed possession dates and agreed compensation as per agreementAUTHORITY07/09/2023
VIKAS PANDEY vs FRONTIE SHELTERS PVT. LTD.Compensation as per RERA rule starting from 01-04-2020 till the delivery of the flat and possession as soon as possible.AUTHORITY07/09/2023
PRATEEK SAXENA vs FRONTIER SHELTERS PVT LTDA clause in the agreement (20.b) which says that the builder is liable to return the entire amount in case of delay. We need the entire amount to be refunded to us and to the bank along with interestAUTHORITY07/09/2023
Vinod P Hanagand vs FRONTIER SHELTERS PVT LTDKindly get into this matter and resolve the issue at the earliest, This builder is big cheater in the market request you to cancel his licenceAUTHORITY07/09/2023
Bidisha Das vs FRONTIER SHELTERS PVT LTDDelay compensation, Pre-EMI Interest and other compensation for financial loss and injuryAUTHORITY07/07/2026
Ravi Ranjan vs Frontier HieghtsDirect Frontier Shelters Pvt Ltd to pay interest for delayed possession at SBI MCLR plus 2 percent from 01 April 2020 until lawful possession with Occupancy Certificate is handed over.AUTHORITY07/07/2026
Rahul Basnotra vs Frontier HieghtsHelp to get Sale Deed, Possession and Interest on delay period (from 31/03/2020 onwards)AUTHORITY07/07/2026
TULASI RAM THOTA vs FRONTIER SHELTERS PVT LTDRequesting RERA authorities to administer builder to compensate customers for the house loan EMI’s paid and upcoming EMI’s till the flat is given possession with OCAUTHORITY06/04/2023
SHIVANGI GOYAL vs FRONTIER SHELTERS PVT LTDI sought for a compensation against delay in unit handover. "No Cancellation or Refund"AUTHORITY05/09/2023
Ujjal Roy vs FRONTIER SHELTERS PVT LTDCompletion of Project at the earliest and provide compensation for the delay, or else refund full amount paid with EMI interest and compensationAUTHORITY05/09/2023
Jatinder Pal Singh vs FRONTIER SHELTERS PVT LTDCompensation from June 2021 to the time they handover the house.AUTHORITY05/09/2023
Hari Krishna Kotigari vs FRONTIER SHELTERS PVT LTDExpectation of confirmed possession dates and agreed compensation as per agreement.AUTHORITY05/06/2026
Abhinav Shankar vs FRONTIER SHELTERS PVT LTDCompensation due to delay in possession as per the agreement and RERA act and speed up the construction pace for handover as we are not getting nay response from the developer.AUTHORITY05/06/2026
Sucharitha R vs FRONTIER SHELTERS PVT LTDPrimarily, proper action must be taken on builder for the project completion delay, put pressure to complete the project soon and secondarily compensation for the delay is also sought.AUTHORITY05/06/2026
Prakash Kumar Sinha vs FRONTIER SHELTERS PVT LTDCompensation for the number of months delayed and the project handover without further delays.AUTHORITY05/06/2026
ASHISH PANDEY vs FRONTIER SHELTERS PVT LTDrefund of 25,60,597/- of PRE-EMI’s from the date of disbursal to 06.04.2024 to May, 2024 as per Loan Statement and Rs. 10,43,273/- paid by complainant along with interest calculated at MCLR + 2% fromAUTHORITY05/06/2026
Himanshu Gupta vs FRONTIER SHELTERS PVT LTDCompensation for the delay in possession, pay interest on the amount paid for delay period, reimburse the additional cost due to delay and expedite the completion and handover of the flatAUTHORITY05/06/2026
Sanjeev Kumar Mishra vs FRONTIER SHELTERS PVT LTDCompensation for the delay in possession, pay interest on the amount paid for delay period, reimburse the additional cost due to delay and expedite the completion and handover of the flatAUTHORITY05/06/2026
Pranab Sureka vs FRONTIER SHELTERS PVT LTDClaim for interest on delay period and Pre-EMIAUTHORITY05/06/2026
Biraja Sankar Nayak vs FRONTIER SHELTERS PVT LTDPlease help me to get my flat and get the interest on delay periodAUTHORITY05/06/2026
Pragyandipta Mohapatra vs FRONTIER SHELTERS PVT LTDPlease help to get my flat and get the interest on delay period from the builderAUTHORITY05/06/2026
KUNDA SEKAR vs FRONTIER SHELTERS PVT LTDa) Grant refund of entire amount of Rs.14,48,380/- paid towards Flat No.3051 with interest. b) grant compensation for the delayAUTHORITY05/06/2026
Rashmi H B vs FRONTIER SHELTERS PVT LTDComplainant prays that this Hon'ble Authority may be pleased to direct the respondent developer to complete the project and hand over the flat as agreed by them with interest for delay periodAUTHORITY05/06/2026
Animesh Ghosh vs FRONTIER SHELTERS PVT LTDComplainant prays that this Hon'ble Authority may be pleased to direct the respondent developer to complete the project and hand over the flat as agreed by them with interest for delay periodAUTHORITY05/06/2026
BALAJI K.S. & G. MAHALAKSHMI vs FRONTIER SHELTERS PVT. LTD.,Compensation for the Delays occurred.AUTHORITY04/07/2023
PRABHAT KUMAR vs FRONTIER SHELTERS PVT LTDCompensation for:- 1. Delay in possession of (Rs 5960 * 12) + 10% 2. Monthly Rs.5960/- till possession 3. Taking more than expected 4. Trapping buyers into false commitmentAUTHORITY01/08/2022

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (44 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/200304/0005638
04-03-2020
Veracity in Payment PlanFRONTIER HEIGHTSDISPOSED AO
CMP/191121/0003948
21-11-2019
Builder cancelled allotment and not provding refund detailsFRONTIER HEIGHTSDISPOSED AO
CMP/220127/0008878
27-01-2022
Delay in Handing over the project /FRONTIER HEIGHTSDISPOSED AUTHORITY FULLBENCH
CMP/220325/0009255
25-03-2022
Long delay and slow progressFRONTIER HEIGHTSDISPOSED AUTHORITY FULLBENCH
CMP/220325/0009254
25-03-2022
Project is delayed for a long time and no progressFRONTIER HEIGHTSDISPOSED AUTHORITY FULLBENCH
CMP/220131/0008886
31-01-2022
Delay in Project deliveryFRONTIER HEIGHTSDISPOSED AUTHORITY FULLBENCH
CMP/220222/0009042
22-02-2022
Compensation on delay in possession and speed up the construction paceFRONTIER HEIGHTSDISPOSED AUTHORITY FULLBENCH
CMP/220206/0008965
06-02-2022
Delay in Flat Handover & No project updateFRONTIER HEIGHTSDISPOSED AUTHORITY FULLBENCH

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectTEAM 2-1975NO 302 EMBASSSY CHAMBERS, NO 5 VITTAL MALLYA ROAD BANGALORE
ContractorSV CONSTRUCTIONS-1997NO 3574 2ND FLOOR, SUGAMA NAGAR OPP DLF NEW TOWN BEGUR
Structural engineerSAI KUMARI T P---

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹40.9 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC KORAMANGALA (IFSC HDFC0000053, a/c …8301). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit.

Location & Connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bellandur–Marathahalli belt5 km
Electronic City6 km
MG Road / city centre12 km
Whitefield IT hub12 km
Outer Ring Road / Manyata18 km
Kempegowda Int'l Airport34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Frontier Shelters.

Other RERA-registered projects in HSR Layout

Major developers building in HSR Layout

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.