RERA Property Intelligence Report · Preview

GEOWN CASPER TRANQUIL

GEOWN CASPER ESTATES · · K-RERA PRM/KA/RERA/1265/347/PR/051225/008312

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
6
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

Registered units
₹3.9 Cr
Est. construction cost
Units profiled
20
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Approved plan numberDPA/TP/LAO/22/2023-24Use this to match the sanctioned drawing set shown by the builder.
Plan approval date23-08-2024
Project start date01-10-2024

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Joint-development titleThis is (at least partly) a joint-development (JDA) project — the landowner and developer split the built units per an agreed ratio. Standard in Bengaluru, but it adds one check: confirm in writing that your specific unit falls in the developer's sale share, and ask to see the JDA's area-sharing clause so there's no dispute over who can sell you the flat.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

⚠ 5 of 19 compliance document slots are filed as under process / not yet usable: Relinquishment Deed, Proforma of Agreement for Sale, Proforma of Allotment Letter, NOC from ESCOMs, NOC for Water.

1 additional compliance slots are filed as Not Applicable.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 20 May 2026 — which has passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)Not found in catalog
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

2 of 3 applicable approvals are on file; still outstanding: KSPCB- PCB (10 Acres to 125 Acres). Pollution-control clearance (KSPCB) is among them — a high-importance clearance, so confirm it has been granted (not just applied for) before you book.

8 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved07-07-2025Water NOC for Geown Casper Tranquil.pdf
KSPCB- PCB (10 Acres to 125 Acres)Applied14-03-2025View NOC
KPTCL- BESCOMApproved25-09-2025Bescom NOC Tranquil.pdf

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Chartered accountant, Engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantA Amaranath2136292022Bengaluru Urban, Karnataka - 560038
EngineerSAJAN DESUZABCC/BL-36/E44632022Bengaluru Urban, Karnataka - 560102

Builder track record

RERA filing

Geown Casper has 6 other K-RERA-registered projects in our records (average reported construction progress 32%). 3 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹3.16 Cr collected from buyers, ₹3.53 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹3.53 Cr) exceeded buyer collections (₹3.16 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress26% → 38% (+12 pts)
Buyer collections in available QPRs₹3.53 Cr
Escrow withdrawals in available QPRs₹3.53 Cr (1.00x collections)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: Axis Bank MICO LAYOUT BNGR KT IFSC Code : UTIB0004216 Pin Code : 560078. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bellandur–Marathahalli belt6 km
MG Road / city centre8 km
Electronic City8 km
Whitefield IT hub14 km
Outer Ring Road / Manyata15 km
Kempegowda Int'l Airport33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Geown Casper. View Geown Casper's full track record →
Geown Casper has 5 projects registered in Bangalore.

Other projects by this builder in Bangalore

Northwinds By Geown & Nivara
Filing overdue · 65% built

Other RERA-registered projects in HSR Layout

Major developers building in HSR Layout

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Geown Casper Tranquil?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 16 Jul 2026