Bangalore/Project record

K-RERA · the public record

GRANDEUR PARK

Bengaluru East · GVG INFRASTRUCTURE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2019declared completionK-RERA registration · read 20 Sep 2026
295registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Flats
91

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

3.3registered acres

90.3registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/171125/000597

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 December 2019
Land area13,221 sq m (3.3 acres)
Homes registered295
Tower/wing entries3
Unit mix91 × Flats

In context

Density90.3 homes per acre
Density in context74th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units295Total inventory registered with K-RERA.
Official carpet area6,529 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area13,221 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.5Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)295Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date05-10-2015

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Flats91100%6,529 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A87474-
B8133133-
C88888-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 294 official flat/unit rows vs 295 registered units disclosed above; ask why the row count differs. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK216543.3-791.0 sqft429.7-538.7 sqft216
3BHK71855.3-1,086.4 sqft583.6-684.1 sqft71
1BHK7469.6 sqft350.6 sqft7

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
B133646.2-900.3 sqft429.7-617.8 sqft133
C88716.9-966.3 sqft444.7-643.5 sqft88
A73469.6-1,086.4 sqft350.6-684.1 sqft73
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
OO2A02BHK543.3 sqft444.6 sqft1
OO3A02BHK543.3 sqft444.6 sqft1
OO4A02BHK543.3 sqft444.6 sqft1
101A13BHK958.4 sqft643.5 sqft1
102A12BHK543.3 sqft444.6 sqft1
103A12BHK543.3 sqft444.6 sqft1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 16 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Dec 2019, extended (Section 6 Extension) to 30 Sep 2021 — both dates have passed with no OC on file. The extension on file was granted on 03 Mar 2020 (K-RERA extension no. EX/PRM/KA/RERA/1251/446/PR/200303/000597) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

1 K-RERA order on this project (PROJECT EXTENSION) — read the order copies on the K-RERA portal.

K-RERA complaint orders (12 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
PRADEEP VASHISTH vs GRANDEUR PARKTo arrange for the refund of whole amount paid by me after availing the Housing loan from SBI because the builder has not given the possession of property to me till nowAUTHORITY18/03/2025
Padmashree Arun Prakash vs M/s.GVG Infrastrucure Pvt Ltd.Full refund of money paid along with interestAUTHORITY13/10/2025
DEBASISH GAYEN vs GRANDEUR PARK AND 27 OTHERSRefund of the entire money collected by the builder from the bank and as well as this complainant along with interest and compensation for the damages incurred.AUTHORITY13/06/2024
REGIL VARUGHESE RAJU vs GVG INFRASTRUCTURE PVT. LTD AND 26 OTHERSRefund of the entire money collected by the builder from the bank and as well as this complaint along with interest and compensation for the damages incurred.AUTHORITY11/06/2024
GOVARDHAN R vs CMRS INFRASTRUCTURE AND 27 OTHERSRefund of the entire money collected by the builder from the bank and as well as this complaint along with interest and compensation for the damages incurred.AUTHORITY11/06/2024
SANJEEV SHARMA vs CMRS INFRASTRUCTURE PVT LTDTo order directing the respondents to repay sum of Rs.70,01,992/- along with the interest at the rate of 24% per annum from the date of filing till date of realization to the complainant & award costAUTHORITY11/06/2024
Ketan Saraf vs GVG INFRASTRUCTURE PVT LTDTo cancel the agreement of sale, Tripartite agreement, refund of amount with interest, to repay the disbursed amount, to settle outstanding dues, to pay litigation/legal cost.AUTHORITY10/09/2026
Pritesh Bari vs GVG INFRASTRUCTURE PVT LTDRefund of the amount with interest along with other appropriate reliefsAUTHORITY08/01/2026
PUSPENDU MUKHERJEE vs CMRS INFRARefund of the entire money collected by the builder from the bank and as well as this complaint along with interest and compensation for the damages incurred.AUTHORITY05/08/2024
Santosh H Bonageri vs CMRS INFRASTRUCTURE PVT LTDRefund of the entire money collected by the builder from the bank and as well as this complainant along with interest and compensation for the damages incurred.AUTHORITY05/02/2025
Tarun Saraf vs GVG INFRASTRUCTURE PVT LTDDirect the Respondents to refund all payments made by the Complainant, including EMIs, and repay the outstanding home loan associated with Account No. 40534925385, obtaining an NOC from SBIAUTHORITY04/03/2025
Saurav Mukherjee vs GVG INFRASTRUCTURE PVT LTDRefund of the entire money collected by the builder from the bank and as well as this complaint along with interest and compensation for the damages incurred.AUTHORITY03/02/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (6 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190307/0002371
07-03-2019
Delivery delay of C-403, Mulberry Mist, VarthurMULBERRY MIST (another project by this promoter)DISPOSED AO
CMP/191210/0004952
10-12-2019
non complication of project and handing over of the possession and agreed compensationMULBERRY MIST (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/200115/0005226
15-01-2020
Delay of delivery of flat and non payment of liquidated damages and breach of agreementMULBERRY MIST (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/200127/0005304
27-01-2020
Compensation for rent since agreement expiredMULBERRY MIST/Grandeur Park (another project by this promoter)DISPOSED AO
CMP/200707/0004260
07-07-2020
Possession of flat or Refund the paid money with interest.MULBERRY MIST (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/221021/0010126
21-10-2022
CMRS not paying installments as per settlement agreement CMP 4952MULBERRY MIST (another project by this promoter)DISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹11.9 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: STATE BANK OF INDIA AECS Layout (IFSC SBIN0040784, a/c …8485). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Whitefield IT hub3 km
Bellandur–Marathahalli belt7 km
Electronic City15 km
MG Road / city centre16 km
Outer Ring Road / Manyata18 km
Kempegowda Int'l Airport29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Gvg Infrastructure.
4 complaints on the K-RERA register against Gvg Infrastructure in Bangalore.

Other RERA-registered projects in Balagere

Major developers building in Balagere

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Grandeur Park?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026