RERA Property Intelligence Report · Preview

RAMKY ONE NORTH PHASE-4

Ramky Estates and Farms · Bengaluru North · K-RERA PRM/KA/RERA/1251/309/PR/171031/001459

Report coverage

K-RERA registry & builder-record report

What this report covers

  • Official K-RERA registry facts — units, cost, land area, towers, approvals
  • Complaint / litigation & compliance history
  • Builder delivery record across their K-RERA portfolio
  • Construction trajectory & sales pace from quarterly filings

To confirm directly with the builder

  • No dimensioned unit layouts could be confidently extracted from the filed plans.
Not yet
Completion certificate
None declared
Legal status
2
Other RERA projects by builder

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk rating, the specific red-flag findings, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the builder before you commit.

Unlock in the ₹999 report →

80
Registered units
₹26.8 Cr
Est. construction cost
Units profiled
21
RERA documents on file

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units80Total inventory registered with K-RERA.
Official carpet area80 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area5,059 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI~1.75Sanctioned floor-area ratio (≈8,833 sqm sanctioned FAR area ÷ 5,059 sqm land) — higher means a denser vertical build.
Registered towers/wings2Official tower/wing count in the K-RERA detail page.
Parking disclosed80 total (0 open) — 1.00 spaces/unitConfirm whether your quoted unit includes an allotted parking space and where it sits.
Project start date01-10-2015

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
APARTMENT FLATS24100%80 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
D-Block44040-
E-Block44040-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 80 official flat/unit rows, matching the 80 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2 BHK2479.6-84.9 sqm42.7-43.8 sqm24
3 BHK2079.6-100.7 sqm42.9-52.2 sqm20
2 BHK +Terrace1279.6 sqm42.9-44.2 sqm12
2 BHK+ Terrace1296.3 sqm42.7-52.2 sqm12
2BHK496.3 sqm50.9 sqm4
3 BHK+ Terrace496.3 sqm43.4-51.6 sqm4
3 BHK+Terrace479.6 sqm43.4-43.6 sqm4

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
D-Block4079.6 sqm42.7-52.2 sqm40
E-Block4082.3-100.7 sqm42.7-52.2 sqm40
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
D1-001D-Block02 BHK79.6 sqm42.7 sqm1
D1-002D-Block02 BHK79.6 sqm42.7 sqm1
D1-003D-Block03 BHK79.6 sqm50.9 sqm1
D1-004D-Block03 BHK79.6 sqm50.9 sqm1
D2-001D-Block02 BHK +Terrace79.6 sqm42.9 sqm1
D2-002D-Block02 BHK +Terrace79.6 sqm42.9 sqm1

What the numbers tell you

Synthesis from the official RERA scale, unit register, and land rows — the read a sales team won't volunteer.

Unit formatAverage official carpet area is ~933 sqft — mid-format homes (2–3BHK territory), not compact stock. This is a boutique, low-density project — 80 homes across 2 towers. Carpet is the RERA-defined usable area, so compare it against the 'super built-up' a broker quotes (typically 25–35% larger).
ParkingThe project declares 80 parking spaces for 80 homes (~1.0 per home) — about one space per home — adequate but tight if you have two cars.
Your land share (UDS)Undivided land share averages ~45 sqm per home; across all 80 homes that is ~72% of the plot — on the lower side — the undivided shares sum to noticeably less than the plot, worth asking the builder why before relying on it. Low UDS relative to land can mean the builder keeps land value the flat owners think they're buying.

🔒 Unit-by-unit guidance · Unit Guidance report

Which block and unit to prefer, the livability read on the filed plans, and a plan-by-plan walkthrough — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full records — land title, amenities paperwork & document catalog · Compliance report

The complete land-title chain, the paperwork behind each declared amenity, and every document row on file with the regulator — the raw records the compliance read is built on.

Unlock in the ₹999 report →

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

1 of 17 compliance document slots are filed as Not Applicable; the remaining 16 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Sep 2018, extended (Section 6 Extension) to 30 Sep 2019 — both dates have passed with no OC on file. The extension on file was granted on 11 Jul 2022 (K-RERA extension no. EX/PRM/KA/RERA/1251/309/PR/220711/001459) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (4 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Anshuman Dwivedi vs Ramky Estates and Farms LimitedComplainant is seeking RERA's intervention to ensure the prompt issuance of the Occupancy Certificate (OC) even post Society formationAUTHORITY09/05/2025
K Swaminathan vs Ramky Estates and Farms LimitedPlease instruct Builder to procure the OC and submit to meAUTHORITY09/05/2025
Anu K Pillai vs Ramky Estates and Farms LimitedI humbly request that you consider issuing a stay order to halt all activities related to the handover/takeover of the project from the promoter until the project receives Occupancy Certificate (OC).AUTHORITY06/05/2026
Deepa Nayak vs Ramky Estates and Farms LimitedPayment of delayed interest(The Fact of the Complaint can not be edited for changing to Delayed interest.Please read compensation as interest)AUTHORITY06/05/2026

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (2 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190529/0003174
29-05-2019
STP & SURVEYRAMKY ONE NORTH PHASE-3 (another project by this promoter)DISPOSED AUTHORITY
CMP/190314/0002374
14-03-2019
Property survey/Landshare/STP/Delay in handing overRAMKY ONE NORTH PHASE-3 (another project by this promoter)DISPOSED AUTHORITY

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectJamuna Chalam-2004S.T.Bed, Koramangala IV th Block.Bengalore
ContractorM/s.Ramky Infrastructure Ltd-1994Gachibowli, Hyderabad
Structural engineerPrakash B V---

Builder track record

RERA filing

Ramky Estates has 2 other K-RERA-registered projects in our records (average reported construction progress 97%). 1 is past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹33.5 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: ICICI Bank MADHAPUR (IFSC ICIC0000040, a/c …0217). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 2 project-photo uploads.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit.

Location & Connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Outer Ring Road / Manyata12 km
Kempegowda Int'l Airport16 km
MG Road / city centre18 km
Bellandur–Marathahalli belt26 km
Whitefield IT hub27 km
Electronic City34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Ramky Estates.
Ramky Estates has 3 projects registered in Bangalore, 1 completed.

Other projects by this builder in Bangalore

Ramky ONE Karnival
Filing overdue · 97% built · 73% sold
Ramky ONE North Phase-3
No filings

Other RERA-registered projects in Yelahanka

Major developers building in Yelahanka

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.