51%construction reportedQ1 2026 filing
16units not bookedof 16 · Q1 2026 filing
14 Apr 2029declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q1 2026 to Q1 2026

declared completion

14 Apr 2029

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3BHK
16

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

0.3registered acres

60.8registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/200626/008730

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion14 April 2029
Land area1,065 sq m (0.3 acres)
Homes registered16
Tower/wing entries1
Unit mix16 × 3BHK

In context

Density60.8 homes per acre
Density in context28th percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units16Total inventory registered with K-RERA.
Official carpet area2,301 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area2,901 sqmUseful scale context when comparing density and project cost.
Registered land area1,065 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)22Separate filed counts; these categories may overlap and are not added together.
Covered-parking field22Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field22Separate filed counts; these categories may overlap and are not added together.
Approved plan numberGBA/BMH/DDTP/0121/25-26Use this to match the sanctioned drawing set shown by the builder.
Plan approval date20-03-2026
Project start date15-04-2026

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3BHK16100%1,728 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Samanvitha projects4162214.99 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 16 official flat/unit rows, matching the 16 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK1694.0-117.0 sqm58.0-72.0 sqm16

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Samanvitha projects1694.0-117.0 sqm58.0-72.0 sqm16
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
101Samanvitha projects13 BHK114.0 sqm72.0 sqm1
102Samanvitha projects13 BHK94.0 sqm58.0 sqm1
103Samanvitha projects13 BHK107.0 sqm65.0 sqm1
104Samanvitha projects13 BHK117.0 sqm71.0 sqm1
201Samanvitha projects23 BHK114.0 sqm72.0 sqm1
202Samanvitha projects23 BHK94.0 sqm58.0 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

16 of 31 compliance document slots are filed as Not Applicable; the remaining 15 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note Fire NOC, environmental clearance and pollution-control clearance (KSPCB) are not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows them as "not found in catalog", that is why; ask the builder directly whether they apply here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

8 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved09-04-2026Bescom_Approval with NOC.pdf
KPTCL- BESCOMApproved23-03-2026Pollution.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantBANDARU RAMBABU2145882016Bengaluru Urban, Karnataka - 560064
EngineerBHASKAR YREG/ACK/0403/23-242023Bengaluru Urban, Karnataka - 560038
ArchitectSASHI KUMAR NERELLACA/2024/1749802024Bengaluru Urban, Karnataka - 560038
ContractorSamanvitha projects-2002Bengaluru Urban, Karnataka - 560043

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹0.00 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.

Construction progress51% → 51% (+0 pts)
Units sold/booked as registered0/16 (0%)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹66.6 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: ICICI Bank ST THOMAS TOWN IFSC Code : ICIC0003158 Pin Code : 560084. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bellandur–Marathahalli belt3 km
Electronic City7 km
MG Road / city centre10 km
Whitefield IT hub11 km
Outer Ring Road / Manyata15 km
Kempegowda Int'l Airport32 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Samanvitha Projects.

Other RERA-registered projects in HSR Layout

Major developers building in HSR Layout

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Samanvitha Siena Terra?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026