Bangalore/Project record

K-RERA · the public record

SLV Green City

Bengaluru North · SLV DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

28 Sep 2018declared completionK-RERA registration · read 20 Sep 2026
120registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

28 Sep 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Residential Apartments
120

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

1.5registered acres

80.0registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/309/PR/180420/001499

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion28 September 2018
Land area6,070 sq m (1.5 acres)
Homes registered120
Tower/wing entries1
Unit mix120 × Residential Apartments

In context

Density80 homes per acre
Density in context56th percentile of 525 Bengaluru North projects (median 75.4)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units120Total inventory registered with K-RERA.
Official carpet area95,570 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area6,070 sqmThe land area attached to this K-RERA registration.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)120Separate filed counts; these categories may overlap and are not added together.
Open-parking field12Separate filed counts; these categories may overlap and are not added together.
Garage field132Separate filed counts; these categories may overlap and are not added together.
Project start date27-09-2016

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Residential Apartments120100%95,570 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
slv green city4120120-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 120 official flat/unit rows, matching the 120 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK91764.0-1,128.0 sqft463.0-684.0 sqft91
3BHK291,064.0-1,128.0 sqft645.0-684.0 sqft29

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
slv green city120764.0-1,128.0 sqft463.0-684.0 sqft120
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1slv green city03BHK1,096.0 sqft664.0 sqft1
2slv green city02BHK816.0 sqft495.0 sqft1
3slv green city03BHK1,088.0 sqft664.0 sqft1
4slv green city02BHK784.0 sqft475.0 sqft1
5slv green city02BHK776.0 sqft470.0 sqft1
6slv green city02BHK776.0 sqft470.0 sqft1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

3 of 16 compliance document slots are filed as Not Applicable; the remaining 13 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 28 Sep 2018 — which has passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)Not found in catalog
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Builder track record

RERA filing

Slv Developers has 6 other K-RERA-registered projects in our records (average reported construction progress 21%). 4 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹18.3 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Hennur main road (IFSC HDFC0002815, a/c …8080). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Outer Ring Road / Manyata5 km
MG Road / city centre13 km
Kempegowda Int'l Airport15 km
Bellandur–Marathahalli belt18 km
Whitefield IT hub18 km
Electronic City27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Slv Developers. View Slv Developers's full track record →
Slv Developers has 7 projects registered in Bangalore.
3 complaints on the K-RERA register against Slv Developers in Bangalore.

Other projects by this builder in Bangalore

SLV Golden Towers
Filing overdue · 21% built · 12% sold

Other RERA-registered projects in Yelahanka

Major developers building in Yelahanka

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in SLV Green City?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026