SOULSPRING PHASE 1

Bengaluru South · SHANKESHWAR LANDMARK

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

57%construction reportedQ1 2026 filing
67units not bookedof 232 · Q1 2026 filing
31 Dec 2028declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

3.5 BHK
24
3 BHK
98
2 BHK
50

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

3.2registered acres

71.4registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/220223/005735

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2028
Land area13,142 sq m (3.2 acres)
Homes registered232
Tower/wing entries2
Unit mix24 × 3.5 BHK, 98 × 3 BHK, 50 × 2 BHK

In context

Density71.4 homes per acre
Density in context40th percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units232Total inventory registered with K-RERA.
Official carpet area19,412 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area65,911 sqmUseful scale context when comparing density and project cost.
Registered land area13,142 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI4.13Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries2Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)232Separate filed counts; these categories may overlap and are not added together.
Covered-parking field172Separate filed counts; these categories may overlap and are not added together.
Open-parking field33Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBBMP/Addl.Dir/JDUse this to match the sanctioned drawing set shown by the builder.
Plan approval date04-10-2021
Project start date01-02-2023

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
3.5 BHK2414%3,098 sqm
3 BHK9857%11,932 sqm
2 BHK5029%4,382 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower 218128128-
Tower 318104104-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 232 official flat/unit rows, matching the 232 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK143107.3-128.6 sqm29.2-36.1 sqm143
2 BHK3578.9-86.4 sqm22.9-26.9 sqm35
3.5 BHK35116.2-129.3 sqm32.2-36.6 sqm35
4 BHK19169.6-187.3 sqm46.8-50.1 sqm38

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower 212878.9-187.3 sqm22.9-50.1 sqm147
Tower 3104107.3-129.3 sqm29.2-36.6 sqm104
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
2001Tower 204 BHK187.3 sqm49.0 sqm2
2005Tower 203 BHK122.0 sqm30.9 sqm1
2006Tower 203 BHK123.6 sqm32.6 sqm1
2007Tower 203.5 BHK128.3 sqm34.7 sqm1
2008Tower 203 BHK121.6 sqm32.2 sqm1
2011Tower 214 BHK171.8 sqm46.8 sqm2

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 35 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

4 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved13-01-2023BWSSBNOC.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved16-05-2022KSPCB.pdf
KSPCB- MOEF (Above 50 Acres)Approved08-07-2025SEIAA NOC.pdf
KPTCL- BESCOMApproved06-02-2026Revised BESCOM NOC - 06-02-2026.pdf
Fire and SafetyApproved17-05-2025Fire NOC.pdf
Airport Authority of IndiaApproved13-03-2025Airport NOC.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantSAURABH TARACHAND JAIN2216862017Bengaluru Urban, Karnataka - 560002
EngineerC ANAND KUMARAM092719-02014Bengaluru Urban, Karnataka - 560016
ArchitectAKSHAY MAHAVEER MEHTACA/2016/786302017Bengaluru Urban, Karnataka - 560027
ContractorSRI VENKATESHWARA EARTH WORK & ROCK CUTTING-1990Bengaluru Urban, Karnataka - 560078

Builder track record

RERA filing

Shankeshwar Landmark has 2 other K-RERA-registered projects in our records (average reported construction progress 21%). 1 is past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹31.23 Cr collected from buyers, ₹31.23 Cr withdrawn from the project's escrow account.

Construction progress52% → 57% (+5 pts)
Units sold/booked as registered165/232 (71%)
Buyer collections in available QPRs₹84.34 Cr
Escrow withdrawals in available QPRs₹84.34 Cr (1.00x collections)
  • Construction progress moved from 52% to 57% across the filed QPR window.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹61.3 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Indian Bank Richmond Circle IFSC Code : IDIB000R018 Pin Code : 560027. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bellandur–Marathahalli belt6 km
Electronic City7 km
MG Road / city centre9 km
Whitefield IT hub13 km
Outer Ring Road / Manyata16 km
Kempegowda Int'l Airport33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Shankeshwar Landmark.
Shankeshwar Landmark has 3 projects registered in Bangalore.

Other projects by this builder in Bangalore

Manikchand Svamitva Soulspring Phase 2
On track · 21% built · 46% sold
Svamitva Emerald Square
No filings

Other RERA-registered projects in HSR Layout

Major developers building in HSR Layout

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.