100%construction reportedQ3 2025 filing
8units not bookedof 25 · Q3 2025 filing
30 Jun 2026declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q3 2025

declared completion

30 Jun 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Villas
25

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

1.9registered acres

13.4registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/030623/005969

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 June 2026
Land area7,572 sq m (1.9 acres)
Homes registered25
Tower/wing entries1
Unit mix25 × Villas

In context

Density13.4 homes per acre
Density in context5th percentile of 1119 Bengaluru East projects (median 75.5)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units25Total inventory registered with K-RERA.
Official carpet area6,042 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area7,828 sqmUseful scale context when comparing density and project cost.
Registered land area7,572 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI3Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)84Separate filed counts; these categories may overlap and are not added together.
Covered-parking field44Separate filed counts; these categories may overlap and are not added together.
Open-parking field108Separate filed counts; these categories may overlap and are not added together.
Garage field44Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBDA/TPM/GH-45/2010-11/2555/2022-2023Use this to match the sanctioned drawing set shown by the builder.
Plan approval date30-12-2022
Project start date02-05-2023

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Villas25100%6,042 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Sterling Villas Grande Phase-3225849.9 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 25 official flat/unit rows, matching the 25 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
C-Rectangular11201.5 sqm278.7 sqm33
B-Rectangular (4 BHK)6280.2 sqm325.2-348.4 sqm24
B-Rectangular (3 BHK)5234.0 sqm325.2 sqm15
C1-Rectangular2321.5 sqm278.7 sqm8
A1-Rectangular1331.8 sqm371.6 sqm4

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Sterling Villas Grande Phase-325201.5-331.8 sqm278.7-371.6 sqm84
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
B-73Sterling Villas Grande Phase-30B-Rectangular (3 BHK)234.0 sqm325.2 sqm3
B-74Sterling Villas Grande Phase-30B-Rectangular (3 BHK)234.0 sqm325.2 sqm3
B-75Sterling Villas Grande Phase-30B-Rectangular (3 BHK)234.0 sqm325.2 sqm3
B-76Sterling Villas Grande Phase-30B-Rectangular (3 BHK)234.0 sqm325.2 sqm3
B-77Sterling Villas Grande Phase-30B-Rectangular (3 BHK)234.0 sqm325.2 sqm3
B-80Sterling Villas Grande Phase-30B-Rectangular (4 BHK)280.2 sqm325.2 sqm4

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

16 of 46 compliance document slots are filed as Not Applicable; the remaining 30 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Jun 2026 — which has passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Complaints on this project's K-RERA page (1 complaint listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/211021/0008458
21-10-2021
NON DELIVERY OF POSSESSION, ILLEGALLY RAISING MAINTENANCE CHARGES, FRAUD AND COMPENSATIONSterling Villa Grande Phase II (another project by this promoter)DISPOSED AUTHORITY BENCH4

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

4 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved27-01-200694VG BWSSB NOC 27012006.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved15-05-20239Upload Renewed KSPCB CFE 1.pdf
KSPCB- MOEF (Above 50 Acres)Approved07-04-201611SEIAANOC Affidavit 1.pdf
KPTCL- BESCOMApproved24-01-200668BESCOM NOC24012006.pdf
Fire and SafetyApproved19-04-202397Fire Force 1.pdf
Airport Authority of IndiaApproved09-01-201498Air force NOC 2014.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantM Padmanabha Bhat0253051987Bengaluru Urban, Karnataka - 560093
EngineerPRAKASH B VBCC/BL/3.2.3/E-784/90-941990Bengaluru Urban, Karnataka - 560040
ArchitectVENKATRAMANAN ASSOCIATESBCC/BL-3.6/A-242:1848/08-091969Bengaluru Urban, Karnataka - 560025
ContractorNEW CONSOLIDATED CONSTRUCTION COMPANY LTD-1946Bengaluru Urban, Karnataka - 560052

Builder track record

RERA filing

Sterling Urban has 2 other K-RERA-registered projects in our records (average reported construction progress 97%). 1 is past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q3): ₹0.00 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.

Construction progress100% → 100% (+0 pts)
Units sold/booked as registered17/25 (68%)

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹92.5 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Kasturba Road Branch, Bangalore IFSC Code : HDFC0000009 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Whitefield IT hub5 km
Bellandur–Marathahalli belt12 km
Outer Ring Road / Manyata16 km
MG Road / city centre18 km
Electronic City22 km
Kempegowda Int'l Airport22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Sterling Urban.
Sterling Urban has 3 projects registered in Bangalore, 2 completed.

Other projects by this builder in Bangalore

Sterling Ascentia
On track · 97% built · 97% sold
Sterling Villa Grande Phase II
No filings

Other RERA-registered projects in Kannamangala

Major developers building in Kannamangala

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.