Bangalore/Project record

K-RERA · the public record

VRUSHABADRI WINTER PARK

Anekal · VRUSHABADRI DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

5%construction reportedQ1 2026 filing
161units not bookedof 167 · Q1 2026 filing
31 Dec 2029declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q1 2026 to Q1 2026

declared completion

31 Dec 2029

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

2 BHK
56
3 BHK
111

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

2.4registered acres

70.9registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/308/PR/070526/008631

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2029
Land area9,537 sq m (2.4 acres)
Homes registered167
Tower/wing entries3
Unit mix56 × 2 BHK, 111 × 3 BHK

In context

Density70.9 homes per acre
Density in context43rd percentile of 471 Anekal projects (median 75.8)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units167Total inventory registered with K-RERA.
Official carpet area14,254 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area26,745 sqmUseful scale context when comparing density and project cost.
Registered land area9,537 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.999Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries3Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)188Separate filed counts; these categories may overlap and are not added together.
Covered-parking field188Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberAPC/CC/1160/2025-26Use this to match the sanctioned drawing set shown by the builder.
Plan approval date02-03-2026
Project start date01-04-2026

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2 BHK5634%4,012 sqm
3 BHK11166%10,242 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
BLOCK - A145518844.55 m
BLOCK - B1356044.55 m
BLOCK - C1356044.55 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 167 official flat/unit rows, matching the 167 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK11178.6-100.4 sqm42.0-51.6 sqm111
2 BHK5668.6-74.5 sqm37.4-38.8 sqm56

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
BLOCK - B5674.5-100.4 sqm38.8-51.6 sqm56
BLOCK - C5668.6-97.7 sqm37.4-50.1 sqm56
BLOCK - A5571.7-100.4 sqm38.5-51.6 sqm55
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A001BLOCK - A13 BHK88.3 sqm45.1 sqm1
A003BLOCK - A12 BHK71.7 sqm38.5 sqm1
A004BLOCK - A13 BHK100.4 sqm51.6 sqm1
A101BLOCK - A23 BHK88.3 sqm45.1 sqm1
A102BLOCK - A23 BHK90.4 sqm48.8 sqm1
A103BLOCK - A22 BHK71.7 sqm38.5 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

⚠ 1 of 24 compliance document slots are filed as under process / not yet usable: Brochure.

1 additional compliance slots are filed as Not Applicable.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (ESCOM/Electricity)
Water & sewage (BWSSB/KWSSB)✓ On file (KWSSB/Water)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Note environmental clearance and pollution-control clearance (KSPCB) are not among the approvals K-RERA marks applicable to this project — if the named-approvals check shows them as "not found in catalog", that is why; ask the builder directly whether they apply here. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

6 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved07-10-2024Water 071024.pdf
KPTCL- BESCOMApproved07-01-2026BESCOM 070126.pdf
Fire and SafetyApproved14-01-2026FIRE FORCE 140126.pdf
Airport Authority of IndiaApproved08-01-2026AAI 080126.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantRAVEENDRA REDDY V.2045512001Bengaluru Urban, Karnataka - 560102
EngineerARUN KUMAR S RBCCL/BL-3.6/SE-0160/23-242010Bengaluru Urban, Karnataka - 560070
ArchitectDISHA K NCA/2025/1931252008Bengaluru Urban, Karnataka - 560070
ContractorK. SRINIVASA RAO-2000Bengaluru Urban, Karnataka - 560008

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹0.09 Cr collected from buyers, ₹0.00 Cr withdrawn from the project's escrow account.

Construction progress5% → 5% (+0 pts)
Units sold/booked as registered6/167 (4%)
Buyer collections in available QPRs₹0.09 Cr
  • The builder has drawn 0.00x of buyer collections from escrow (about 0% of the ₹0 Cr collected) — money is largely staying in the regulated escrow account rather than being pulled out ahead of spend, which is the safer direction. A ratio near or above 1.0 would be the one to scrutinise.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹60.5 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Bank of Baroda. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Whitefield IT hub8 km
Bellandur–Marathahalli belt10 km
Electronic City14 km
MG Road / city centre20 km
Outer Ring Road / Manyata23 km
Kempegowda Int'l Airport33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Vrushabadri Developers.
Vrushabadri Developers has 2 projects registered in Bangalore.

Other projects by this builder in Bangalore

Vrushabadri Spring Park
On track · 57% built · 49% sold

Other RERA-registered projects in Balagere

Major developers building in Balagere

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Vrushabadri Winter Park?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026